Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
April 2, 2026
PROJECT UPDATE
NORTH PARK ROAD IMPROVEMENTS – JAMES WATTERS
The new detour route to Robert’s Ferry was put up on March 3rd and North Park Road was closed to traffic
on March 9th. Construction resumed later the same week.
The primary work item for the month of March was water main. As of the week of March 30th, the majority
of the remaining water main on the project is complete with some service connections and small
adjustments yet to be finished. A section of unmarked and untraceable water main was discovered on the
north side of Mopar Drive approximately 150 feet east of the expected tie-in point. Damage to this section
was repaired and the connection installed the week of March 23rd.
Access for homeowners at 300 North Park Road has been established and contact information has been
provided to them. Their access will be maintained throughout the remainder of the project and changes
will be communicated promptly.
Some site access concerns have been reported. Local traffic and construction traffic from adjacent sites
have been moving traffic control devices to enter the project site. The Johnson County Sheriff’s Office has
been kept informed of these incidents and has instructed on-site personnel to collect license plates of
trespassers.
Moving forward, storm sewer work began the week of March 30th and paving is tentatively planned for May
or June. Coordination between the North Park Road project and the Homemakers site is ongoing.
A Change Order for the Homemakers site has been submitted for Council approval the week of March 30th.
PROJECT UPDATE
Page 3 of 6
Sources
- revize: L.1 (qbSs9LxUFCc343YmzNOV7epOV9o1z5.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-1 Engineer's Report
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.