Design/Action Items Accomplishments • N/A Upcoming Submittals/Design Deliverables • ASI-14: SW Mechanical Screen Update – Confirming sidewalk to new gate location Submittals • N/A • Will begin to start working on O&M items that can be submitted Requests for Information • 29 Total RFI’s • 3 RFI’s this month • 0 Pending answers ‒ 0 over due Areas of Concern / Focus • ASI’s to be released: ‒ SW mechanical screen door move • Updating WAP and camera locations based on owner suppliers Get involved, respond with urgency, and work as a team to get the job done. Leverage the strengths of each individual and overcome obstacles as one. Owner Progress Report | 250120 March 2026 Miron Construction Co., Inc. | 6

Sources

Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.