Text from the PDF text layer; check the PDF for anything that matters.Executive Summary
Overview
March was the month for interior improvement! During this past month we were able to accomplish the entirety of
interior steel erection and have 95% of our concrete floors poured. We will be wrapping up the slab on grade (last
interior pour) in the first week of April. We progressed on the exterior metal siding from the South to the North with
wrapping up the West side this coming month. With the floors poured on the main floor and 2nd floor we are now able
to start our interior rough in. This will be the major activity in April and bringing the building to life.
Major Milestones / Accomplishments
• All interior steel is complete
• Slab on metal deck is completed
• Exterior duct work is installed
Upcoming Milestones
• 1st In wall inspection (April 17th)
• Completion of exterior metal siding
Key Issues and Concerns
• Finalizing owner supplied equipment and getting owner contractors/vendors on board
Be authentic, lead with
humility, and recognize the
needs of others. Care for one
another and extend a helping
hand wherever it’s needed.
Honor our history.
Owner Progress Report | 250120 March 2026 Miron Construction Co., Inc. | 5
Sources
- revize: L.3 (fFudCGH94JrIS7QxXB1pu8HoRlrF0x.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.