staff report memo · L-3
Tiffin Recreation Center Monthly Report — L.3
Page 18 of 19
Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 4/03/26
Miron Construction Co., Inc. Data Date: 03-Apr-26
Page 4 of 4
250120-43PM 20260403
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2026
Dur Dur Nov
Apr May Jun Jul Aug Sep Oct
1800 MIRON 1790 Final Completion 0 0 29-Oct-26
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: L.3 (fFudCGH94JrIS7QxXB1pu8HoRlrF0x.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.