staff report memo · L-3
Tiffin Recreation Center Monthly Report — L.3
Page 17 of 19
Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 4/03/26
Miron Construction Co., Inc. Data Date: 03-Apr-26
Page 3 of 4
250120-43PM 20260403
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2026
Dur Dur Nov
Apr May Jun Jul Aug Sep Oct
3080 MIRON DOOR 1620, 2090 Door and Hardware Installation 8 8 19-Jun-26 30-Jun-26
3000
2910 H2I 1680, 1720 Gym Equipment - Installation 20 20 23-Jun-26 21-Jul-26
3220
2870 PRICEELEC 3270, 1760, 1st Floor - Electrical Trim and Lig hts 10 10 26-Jun-26 10-Jul-26
1620, 1650
2880 ILTENS 1630
1630 1820, 1st Floor - Diffusers 10 10 26-Jun-26 10-Jul-26
2090
1650 CEILING 1630, 1820 1st Floor Ceiling Tile - Drop 2 2 13-Jul-26 14-Jul-26
2870
2090 ILTENS 3080, 1720, HVAC Startup 3 3 13-Jul-26 15-Jul-26
2880 1820,
3250 TRI CITY FP 1630 1810,
2860, Fire Protection - Trim Out Heads 4 4 13-Jul-26 16-Jul-26
1740,
1810 PHILLIPSFLR 2090 1730
1760 Athletic Flooring - 2nd Floor 15 15 16-Jul-26 05-Aug-26
1730 PHILLIPSFLR 3250, 1760 Flooring - Turf Area 10 10 17-Jul-26 30-Jul-26
1620,
1740 APPLEBY 2090,
3250, 2080, Soft Goods Flooring - 1st Floor 10 10 17-Jul-26 30-Jul-26
1630, 2920
2080 GENTRADES 1830,
3100, 1640, Architectural Casework Install 15 15 17-Jul-26 06-Aug-26
1620, 1760
2860 PHILLIPSFLR 1680,
3250, 1720 Athletic Flooring - 1st Floor 10 10 17-Jul-26 30-Jul-26
2090
1720 H2I 1970, 1820 Wood Flooring - Gym Area 30 30 31-Jul-26 11-Sep-26
1620,
2920 MIRON DOOR 2090,
1740, 1820 Interior Door and Harware Installation 5 5 31-Jul-26 06-Aug-26
2990,
1640 AAAMECH 3000
2080, 1770 1st Floor Plumbing Fixtures 5 5 07-Aug-26 13-Aug-26
1630,
1820 MEP 3020
1720, 1760, Test & Balance 9 9 14-Sep-26 24-Sep-26
1650, 1880
1880 MEP 2090,
1820 1760 Commissioning 9 9 25-Sep-26 07-Oct-26
WEATHER CONTINGENCY 141 141 06-Apr-26 22-Oct-26
WEATHER CONTINGENCY SITE WORK BP1 0 0 06-Apr-26 06-Apr-26
1750 MIRON 2040 Weather Contingency Sitework (May '25-July'25 6 Days) 0 0 06-Apr-26 06-Apr-26
CRITICAL 0 0
NON-CRITICAL 0 0
WEATHER CONTINGENCY CONSTRUCTION BP2 2 2 21-Oct-26 22-Oct-26
1890 MIRON 1770 1780 Weather Contingency Construction (Sept '25-Jan '26 12 Days) 2 2 21-Oct-26 22-Oct-26
CRITICAL 0 0
NON-CRITICAL 0 0
CONSTRUCTION BULLETINS 0 0
PROJECT COMPLETION 25 25 25-Sep-26 29-Oct-26
1760 MIRON 1820, 1770 Quality Control Review 10 10 25-Sep-26 08-Oct-26
1870,
1770 MIRON 1880,
1640, 1890, Punchlist 8 8 09-Oct-26 20-Oct-26
1700, 1780
1780 MIRON 1760
1890, 1790 Substantial Completion 0 0 22-Oct-26*
1770
1790 MIRON 1780 1800 Punchlist Corrections 5 5 23-Oct-26 29-Oct-26
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: L.3 (fFudCGH94JrIS7QxXB1pu8HoRlrF0x.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.