Discussion and Consideration of Pay Application #11 – Miron Construction – Tiffin Recreation Center Project – Motion to Approve — K.3
Page 4 of 5
Text read by the vision model; check the PDF for anything that matters.<table>
<tr>
<th rowspan="2">ITEM NO.</th>
<th rowspan="2">DESCRIPTION OF WORK</th>
<th colspan="3">SCHEDULED VALUE</th>
<th colspan="2">WORK COMPLETED (D+E)</th>
<th rowspan="2">MATERIAL PRESENTLY STORED</th>
<th rowspan="2">TOTAL COMPLETED AND STORED TO DATE</th>
<th rowspan="2">PER-%(G/C) TO DATE</th>
<th rowspan="2">BALANCE TO FINISH</th>
<th rowspan="2">RETAINAGE</th>
</tr>
<tr>
<th>ORIGINAL</th>
<th>CHANGE ORDERS</th>
<th>CURRENT</th>
<th>FROM PREVIOUS APPLICATION</th>
<th>THIS PERIOD</th>
</tr>
<tr>
<td>110</td>
<td>Metal Building Systems</td>
<td>1,997,300.00</td>
<td>24,775.83</td>
<td>2,022,075.83</td>
<td>1,727,912.96</td>
<td>34,430.62</td>
<td>0.00</td>
<td>1,762,343.58</td>
<td>87</td>
<td>259,732.25</td>
<td>88,117.18</td>
</tr>
<tr>
<td>115</td>
<td>Elevators</td>
<td>122,000.00</td>
<td>0.00</td>
<td>122,000.00</td>
<td>61,000.00</td>
<td>0.00</td>
<td>0.00</td>
<td>61,000.00</td>
<td>50</td>
<td>61,000.00</td>
<td>3,050.00</td>
</tr>
<tr>
<td>120</td>
<td>Fire Suppression</td>
<td>204,120.00</td>
<td>-46,930.90</td>
<td>157,189.10</td>
<td>51,276.00</td>
<td>0.00</td>
<td>0.00</td>
<td>51,276.00</td>
<td>33</td>
<td>105,913.10</td>
<td>2,563.80</td>
</tr>
<tr>
<td>125</td>
<td>Plumbing</td>
<td>383,200.00</td>
<td>-61,603.00</td>
<td>321,597.00</td>
<td>82,341.00</td>
<td>11,746.75</td>
<td>0.00</td>
<td>94,087.75</td>
<td>29</td>
<td>227,509.25</td>
<td>4,704.39</td>
</tr>
<tr>
<td>130</td>
<td>HVAC</td>
<td>935,847.00</td>
<td>-213,737.00</td>
<td>722,110.00</td>
<td>358,198.00</td>
<td>97,548.00</td>
<td>0.00</td>
<td>455,746.00</td>
<td>63</td>
<td>266,364.00</td>
<td>22,787.30</td>
</tr>
<tr>
<td>135</td>
<td>Electrical</td>
<td>823,355.00</td>
<td>-113,688.39</td>
<td>709,666.61</td>
<td>306,237.88</td>
<td>31,980.12</td>
<td>0.00</td>
<td>338,218.00</td>
<td>48</td>
<td>371,448.61</td>
<td>16,910.90</td>
</tr>
<tr>
<td>140</td>
<td>Earthwork</td>
<td>315,386.00</td>
<td>12,788.20</td>
<td>328,174.20</td>
<td>285,101.44</td>
<td>4,961.02</td>
<td>0.00</td>
<td>290,062.46</td>
<td>88</td>
<td>38,111.74</td>
<td>14,503.12</td>
</tr>
<tr>
<td>145</td>
<td>Aggregate Piers</td>
<td>135,379.00</td>
<td>0.00</td>
<td>135,379.00</td>
<td>135,379.00</td>
<td>0.00</td>
<td>0.00</td>
<td>135,379.00</td>
<td>100</td>
<td>0.00</td>
<td>6,768.95</td>
</tr>
<tr>
<td>150</td>
<td>Asphalt Paving</td>
<td>169,606.00</td>
<td>1,249.00</td>
<td>170,855.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>170,855.00</td>
<td>0.00</td>
</tr>
<tr>
<td>155</td>
<td>Concrete Site Work</td>
<td>82,800.00</td>
<td>416.63</td>
<td>83,216.63</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>83,216.63</td>
<td>0.00</td>
</tr>
<tr>
<td>160</td>
<td>Athletic Turf Surfacing</td>
<td>45,000.00</td>
<td>-5,500.00</td>
<td>39,500.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>39,500.00</td>
<td>0.00</td>
</tr>
<tr>
<td>165</td>
<td>Site Utilities</td>
<td>64,708.00</td>
<td>75,782.88</td>
<td>140,490.88</td>
<td>140,490.88</td>
<td>0.00</td>
<td>0.00</td>
<td>140,490.88</td>
<td>100</td>
<td>0.00</td>
<td>7,024.55</td>
</tr>
<tr>
<td>166</td>
<td>Landscaping</td>
<td>0.00</td>
<td>97,075.00</td>
<td>97,075.00</td>
<td>20,360.00</td>
<td>0.00</td>
<td>0.00</td>
<td>20,360.00</td>
<td>21</td>
<td>76,715.00</td>
<td>1,018.00</td>
</tr>
<tr>
<td>170</td>
<td>Testing & Inspections Allowance</td>
<td>40,000.00</td>
<td>0.00</td>
<td>40,000.00</td>
<td>18,157.50</td>
<td>950.00</td>
<td>0.00</td>
<td>19,107.50</td>
<td>48</td>
<td>20,892.50</td>
<td>955.38</td>
</tr>
<tr>
<td>175</td>
<td>New Utility Services Allowance</td>
<td>40,000.00</td>
<td>-14,543.95</td>
<td>25,456.05</td>
<td>9,395.17</td>
<td>0.00</td>
<td>0.00</td>
<td>9,395.17</td>
<td>37</td>
<td>16,060.88</td>
<td>469.76</td>
</tr>
<tr>
<td>180</td>
<td>Mill & Overlay N Parking Lot Allowance</td>
<td>101,000.00</td>
<td>0.00</td>
<td>101,000.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>101,000.00</td>
<td>0.00</td>
</tr>
<tr>
<td>185</td>
<td>Flood Insurance Deductible Allowance</td>
<td>25,000.00</td>
<td>0.00</td>
<td>25,000.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>25,000.00</td>
<td>0.00</td>
</tr>
<tr>
<td>190</td>
<td>CMU Enhancements Allowance</td>
<td>35,000.00</td>
<td>-35,000.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>195</td>
<td>Lobby Alternate Ceiling Allowance</td>
<td>45,000.00</td>
<td>-45,000.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>200</td>
<td>Data Cabling & Backbone Allowance</td>
<td>250,000.00</td>
<td>-250,000.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>0.00</td>
<td>0.00</td>
</tr>
<tr>
<td>205</td>
<td>Access Control Allowance</td>
<td>34,000.00</td>
<td>0.00</td>
<td>34,000.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>34,000.00</td>
<td>0.00</td>
</tr>
<tr>
<td>210</td>
<td>CCTV Allowance</td>
<td>45,000.00</td>
<td>0.00</td>
<td>45,000.00</td>
<td>0.00</td>
<td>24,403.46</td>
<td>0.00</td>
<td>24,403.46</td>
<td>54</td>
<td>20,596.54</td>
<td>1,220.17</td>
</tr>
</table>
Sources
- revize: K.3 (cRJfYutXbEiOEsYqeqgWICI65m0sA3.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-3 Discussion and Consideration of Pay Application #11 – Miron Construction – Tiffin...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.