contract agreement · K-3
Discussion and Consideration of Pay Application #11 – Miron Construction – Tiffin Recreation Center Project – Motion to Approve — K.3
Page 3 of 5
Text read by the vision model; check the PDF for anything that matters.<table>
<tr>
<th rowspan="2">ITEM NO.</th>
<th rowspan="2">DESCRIPTION OF WORK</th>
<th colspan="3">SCHEDULED VALUE</th>
<th colspan="2">WORK COMPLETED (D+E)</th>
<th rowspan="2">MATERIAL PRESENTLY STORED</th>
<th rowspan="2">TOTAL COMPLETED AND STORED TO DATE</th>
<th rowspan="2">PERCENTAGE(G/C)</th>
<th rowspan="2">BALANCE TO FINISH</th>
<th rowspan="2">RETAINAGE</th>
</tr>
<tr>
<th>ORIGINAL</th>
<th>CHANGE ORDERS</th>
<th>CURRENT</th>
<th>FROM PREVIOUS APPLICATION</th>
<th>THIS PERIOD</th>
</tr>
<tr>
<td>005</td>
<td>General Conditions</td>
<td>503,136.00</td>
<td>6,000.00</td>
<td>509,136.00</td>
<td>267,291.00</td>
<td>31,446.00</td>
<td>0.00</td>
<td>298,737.00</td>
<td>59</td>
<td>210,399.00</td>
<td>14,936.85</td>
</tr>
<tr>
<td>010</td>
<td>General Requirements</td>
<td>206,878.00</td>
<td>0.00</td>
<td>206,878.00</td>
<td>90,131.41</td>
<td>16,423.96</td>
<td>0.00</td>
<td>106,555.37</td>
<td>52</td>
<td>100,322.63</td>
<td>5,327.82</td>
</tr>
<tr>
<td>015</td>
<td>Construction Manager Contingency</td>
<td>567,585.00</td>
<td>-154,781.41</td>
<td>412,803.59</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>412,803.59</td>
<td>0.00</td>
</tr>
<tr>
<td>016</td>
<td>Owner Contingency</td>
<td>0.00</td>
<td>225,451.17</td>
<td>225,451.17</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>225,451.17</td>
<td>0.00</td>
</tr>
<tr>
<td>020</td>
<td>Construction Fee</td>
<td>500,822.00</td>
<td>-42,001.00</td>
<td>458,821.00</td>
<td>368,121.28</td>
<td>14,832.39</td>
<td>0.00</td>
<td>382,953.67</td>
<td>83</td>
<td>75,867.33</td>
<td>19,147.61</td>
</tr>
<tr>
<td>025</td>
<td>Preconstruction Services</td>
<td>10,000.00</td>
<td>0.00</td>
<td>10,000.00</td>
<td>10,000.00</td>
<td>0.00</td>
<td>0.00</td>
<td>10,000.00</td>
<td>100</td>
<td>0.00</td>
<td>500.00</td>
</tr>
<tr>
<td>030</td>
<td>Railroad Insurance</td>
<td>5,050.00</td>
<td>0.00</td>
<td>5,050.00</td>
<td>5,050.00</td>
<td>0.00</td>
<td>0.00</td>
<td>5,050.00</td>
<td>100</td>
<td>0.00</td>
<td>252.50</td>
</tr>
<tr>
<td>035</td>
<td>Cast In Place Concrete</td>
<td>813,985.00</td>
<td>87,587.70</td>
<td>901,572.70</td>
<td>438,120.94</td>
<td>296,596.61</td>
<td>0.00</td>
<td>734,717.55</td>
<td>81</td>
<td>166,855.15</td>
<td>36,735.88</td>
</tr>
<tr>
<td>040</td>
<td>Masonry</td>
<td>344,553.00</td>
<td>-166,080.78</td>
<td>178,472.22</td>
<td>164,972.22</td>
<td>7,500.00</td>
<td>0.00</td>
<td>172,472.22</td>
<td>97</td>
<td>6,000.00</td>
<td>8,623.61</td>
</tr>
<tr>
<td>045</td>
<td>Steel Fabrication and Erection</td>
<td>987,710.00</td>
<td>108,545.80</td>
<td>1,096,255.80</td>
<td>938,040.25</td>
<td>81,944.50</td>
<td>0.00</td>
<td>1,019,984.75</td>
<td>93</td>
<td>76,271.05</td>
<td>50,999.25</td>
</tr>
<tr>
<td>050</td>
<td>General Trades</td>
<td>327,150.00</td>
<td>71,718.84</td>
<td>398,868.84</td>
<td>12,486.97</td>
<td>27,017.33</td>
<td>0.00</td>
<td>39,504.30</td>
<td>10</td>
<td>359,364.54</td>
<td>1,975.22</td>
</tr>
<tr>
<td>055</td>
<td>Rolling Doors and Shutters</td>
<td>6,890.00</td>
<td>1,870.00</td>
<td>8,760.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>8,760.00</td>
<td>0.00</td>
</tr>
<tr>
<td>060</td>
<td>Alum Windows, Entrances, Glass/Glazing</td>
<td>611,932.00</td>
<td>-222,632.00</td>
<td>389,300.00</td>
<td>182,815.00</td>
<td>0.00</td>
<td>0.00</td>
<td>182,815.00</td>
<td>47</td>
<td>206,485.00</td>
<td>9,140.75</td>
</tr>
<tr>
<td>065</td>
<td>Gypsum Board Systems</td>
<td>320,909.00</td>
<td>-107,219.00</td>
<td>213,690.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>213,690.00</td>
<td>0.00</td>
</tr>
<tr>
<td>070</td>
<td>Tile</td>
<td>13,129.00</td>
<td>2,934.00</td>
<td>16,063.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>16,063.00</td>
<td>0.00</td>
</tr>
<tr>
<td>075</td>
<td>Suspended Acoustical Ceiling and Panels</td>
<td>117,427.00</td>
<td>-27,246.00</td>
<td>90,181.00</td>
<td>0.00</td>
<td>18,169.00</td>
<td>0.00</td>
<td>18,169.00</td>
<td>20</td>
<td>72,012.00</td>
<td>908.45</td>
</tr>
<tr>
<td>080</td>
<td>Resilient Athletic Flooring</td>
<td>269,255.00</td>
<td>-41,205.00</td>
<td>228,050.00</td>
<td>818.00</td>
<td>0.00</td>
<td>0.00</td>
<td>818.00</td>
<td>0</td>
<td>227,232.00</td>
<td>40.90</td>
</tr>
<tr>
<td>085</td>
<td>Wood Athletic Flooring</td>
<td>240,000.00</td>
<td>-40,307.00</td>
<td>199,693.00</td>
<td>9,985.00</td>
<td>0.00</td>
<td>0.00</td>
<td>9,985.00</td>
<td>5</td>
<td>189,708.00</td>
<td>499.25</td>
</tr>
<tr>
<td>090</td>
<td>Resilient Flooring, Base and Carpet</td>
<td>67,829.00</td>
<td>-46,219.00</td>
<td>21,610.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>21,610.00</td>
<td>0.00</td>
</tr>
<tr>
<td>095</td>
<td>Painting and Wall Covering</td>
<td>161,504.00</td>
<td>-72,450.50</td>
<td>89,053.50</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>89,053.50</td>
<td>0.00</td>
</tr>
<tr>
<td>100</td>
<td>Building Signage</td>
<td>80,097.00</td>
<td>20,203.00</td>
<td>100,300.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0.00</td>
<td>0</td>
<td>100,300.00</td>
<td>0.00</td>
</tr>
<tr>
<td>105</td>
<td>Athletic Equipment</td>
<td>300,600.00</td>
<td>12,745.00</td>
<td>313,345.00</td>
<td>15,667.00</td>
<td>0.00</td>
<td>0.00</td>
<td>15,667.00</td>
<td>5</td>
<td>297,678.00</td>
<td>783.35</td>
</tr>
</table>
Sources
- revize: K.3 (cRJfYutXbEiOEsYqeqgWICI65m0sA3.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-3 Discussion and Consideration of Pay Application #11 – Miron Construction – Tiffin...