contract agreement · K-4
Discussion and Consideration of Change Order #15 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.4
Page 5 of 5
Text from the PDF text layer; check the PDF for anything that matters.Doc Express® Document Signing History
Contract: 52-7662-615 Document: change_order-15-20260423
This document is in the process of being signed by all required signatories using the Doc Express® service.
Following are the signatures that have occurred so far.
Date Signed By
Dakota Simonsen
04/24/2026 Boomerang Corp.
Electronic Signature
(Approved by Contractor)
James Watters
MSA Professional Svs
04/27/2026
Electronic Signature
(Recommended by Engineer / Approved)
(Approved by PIRC (when applicable))
(Approved by Administering Bureau or designee)
(Approved by FHWA (when applicable))
Sources
- revize: K.4 (Et92sVw4SNm9ZmWnFH0prXVSscU83u.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Change Order #15 – Boomerang Corporation – North Park...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.