staff report memo · L-3
Tiffin Recreation Center Monthly Report — L.3
Page 8 of 18
Text from the PDF text layer; check the PDF for anything that matters.Construction Summary
Schedule Update
Scheduled April Activities: Scheduled May Activities:
• Foundation backfill (95%) • Hang and finish drywall
• PEMB Roofing (100%) • Continuing with Mechanical, Electrical,
• PEMB exterior metal panels (100%) Plumbing (MEP) rough in’s (in wall and
• Slab on grade (100%) overhead)
• Interior metal studs (85%) • Painting
• Mechanical, Electrical, Plumbing (MEP) rough in’s
‒ Inwall (90%)
‒ Overhead (50%)
• Hanging drywall (15%)
Manpower Report
List of major subcontractors & number of employees onsite:
Total number of employees: 35
• AAA Mechanical – 4
• Cedar Valley Steel – 2 • Pearson Wall Systems – 4
• Ilten’s – 3 • Price Electric – 3
• Merit Construction – 1 • SG Construction – 8
• Miron Concrete/General Trades – 6 • Tri-City Fire Protection – 2
• Miron Construction Manager – 2
Delays
• Weather – See Daily Log Weather Report
‒ 0 days in April
• Weather delays are no longer on critical path and will be removed.
• Materials & Labor
‒ N/A
Key Issues / Concerns & Recommended Action Steps
• Drywall contractor manpower – increased workers the last week of April Deliver unmatched quality,
create meaningful
connections, and craft
unforgettable experiences in
everything we do. Capture
what truly matters and find
ways to inspire.
Owner Progress Report | 250120 April 2026 Miron Construction Co., Inc. | 8
Sources
- revize: L.3 (EXLhDbZWkTgTDqx1GIAhgcbPWRYtzN.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.