staff report memo · L-3
Tiffin Recreation Center Monthly Report — L.3
Page 5 of 18
Text from the PDF text layer; check the PDF for anything that matters.Executive Summary
Overview
Major progress has been made in the month of April. We were able to get all the exterior metal siding, facia, and
gutters completed. On the inside, metal studs have brought the space to life. Interior framing is progressing on the
North side while drywall is being installed in the Southwest corner. Our mechanical, plumbing, electrical, and fire
protection contractors have been busy as well. In wall rough-ins are around 90% complete with all plumbing
completed. Overhead ductwork is being ran throughout the first floor, while fire protection lines have been installed on
2nd floor and on the North side. Interior metal siding on 2nd floor has begun installation as well. Our concrete team
finished all interior pours this month with the gym floor and the concrete bench.
Major Milestones / Accomplishments
• Exterior metal panels, facia, and gutters complete
• All interior concrete is poured
Upcoming Milestones
• Start of drywall taping and sanding activities
• Start of interior painting (end of May)
Key Issues and Concerns
• Staying on top of any last-minute rough-in additions, i.e. motorized shades
Be authentic, lead with
humility, and recognize the
needs of others. Care for one
another and extend a helping
hand wherever it’s needed.
Honor our history.
Owner Progress Report | 250120 April 2026 Miron Construction Co., Inc. | 5
Sources
- revize: L.3 (EXLhDbZWkTgTDqx1GIAhgcbPWRYtzN.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.