Minutes: Regular Meeting 06/02/2026
Page 1 of 4
Text from the PDF text layer; check the PDF for anything that matters.`
City of Tiffin, Iowa
Meeting: Tiffin City Council Meeting
Place: Tiffin City Hall 300 Railroad St, Tiffin, Iowa, 52340
Date/Time: June 2, 2026 – 7:00 p.m.
Web Page: www.tiffin-iowa.org
Posted: May 29, 2026 (website & front entry of City Hall)
Mayor: Tim Kasparek W/WW Superintendent: Brett Mehmen
Council At Large: Tim Orris – Mayor Pro-Tem D. of Public Works: Brian Detert
Council At Large: Tony Johnson Recreation Director: Grant Weber
Council At Large: Skylar Limkemann Building Official: Brian Shay
Council At Large: Chris Olney Library Director: Liz Petersen Grier
Council At Large: Eric Schnedler Interim Fire Chief: Tom Hartshorn
City Administrator: Doug Boldt City Engineer: MSA Professional Services
Asst. City Administrator: Ashley Platz
City Clerk: Abigail Hora
City Attorney: Crystal Raiber
Work Session - Call to Order – 5:30 PM
A. Roll Call
The City of Tiffin City Council held a work session Tuesday, June 2, 2026, at the Tiffin City Hall Council
Chambers. Mayor Kasparek called the meeting to order at 5:30 PM. Upon roll being called the following
members were present: Chris Olney, Tim Orris, Eric Schnedler, Tony Johnson and Skylar Limkemann
arrived at 5:37 PM. Others present were City Administrator Doug Boldt, Assistant City Administrator
Ashley Platz and City Clerk Abigail Hora.
B. Agenda Additions/Agenda Approval
Motion to approve agenda by Olney.
Second by Johnson.
All ayes, agenda approved.
C. Discussion and Review of Highway 6 Reconstruction Project Staging Plan
Discussion: James Watters was present to discuss the staging plans for the Highway 6 project. For 2027,
Phases 1 and 2 were reviewed. A detour was expected to be in place from March through November.
Construction efforts were to focus first on correcting Croell Ave, while maintaining two-way access to Hawk
Wash and Tiffin Iron Tap. Phase 1 was designed to maintain access to the baseball fields and park via
Kimberlite St. Southbound traffic from Croell Ave to Highway 6 would not have access from March through
November. The roadway was expected to reopen during the winter months, with no detour anticipated from
November through March. For 2028, Phase 2 was discussed. A detour was again expected to be in place
from March through November. The Croell Ave and Kimberlite St intersections with Highway 6 were
planned to remain open, and the Kimberlite St signal would remain operational. Due to the more urbanized
nature of this phase of construction, temporary parking along side roads would be required for residents.
Access to Highway 6 from Main St, Summerhays, South Brown St, and Stephens St would be closed during
construction. Final plans are expected to be submitted to the Iowa DOT in July, with the project anticipated
to be bid in October. The priority was to complete work on Croell Ave during Phases 1 and 2, followed by
Stephens St during Phase 3. A frequently asked questions (FAQ) document was planned to be developed
prior to the start of construction in 2027.
D. Discussion and Review of Kinetic Fiber Network Installation Proposal – Matt Graham
Discussion: Matt Graham was present to discuss Kinetic Fiber's proposal to install a citywide fiber-optic
network within Tiffin's public rights-of-way and utility easements. The project would expand access to high-
speed internet, increase competition among service providers, and improve reliability for residents and
businesses. Graham explained that construction methods are designed to minimize surface disruption and
that Kinetic would be responsible for repairing any damages caused during installation. The proposal also
includes plans to transition customers from aging copper infrastructure to fiber service and identifies the
proposed service area within the community.
City Council Agenda Page 1 of 4