staff report memo · K-6
Discussion and Consideration of Approval of State Revolving Fund (SRF) Reimbursement Request #6 – Water Treatment Facility Upgrade Project – Motion to Approve — K.6
Page 11 of 14
Text read by the vision model; check the PDF for anything that matters.Progress Estimate - Lump Sum Work
<table>
<tr>
<th>Application No.: 10</th>
<th>Application Period:</th>
<th>From</th>
<th>05/21/26</th>
<th>to</th>
<th>06/26/26</th>
<th>Application Date:</th>
<th>06/26/26</th>
</tr>
<tr>
<td>211</td>
<td>Process Piping Materials</td>
<td>$111,340.84</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>111,340.84</td>
</tr>
<tr>
<td>212</td>
<td>Process Piping Labor</td>
<td>$85,502.50</td>
<td>2,137.56</td>
<td></td>
<td>2,137.56</td>
<td>2%</td>
<td>83,364.94</td>
</tr>
<tr>
<td>213</td>
<td>Valves Materials</td>
<td>$83,000.00</td>
<td></td>
<td>29,765.00</td>
<td>29,765.00</td>
<td>36%</td>
<td>53,235.00</td>
</tr>
<tr>
<td>214</td>
<td>Valves Labor</td>
<td>$30,614.26</td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>30,614.26</td>
</tr>
<tr>
<td>215</td>
<td>Structure 30 - Clearwell</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>216</td>
<td>Process Piping Materials</td>
<td>$62,822.42</td>
<td>7,658.00</td>
<td></td>
<td>2,820.00</td>
<td>10,478.00</td>
<td>17%</td>
<td>52,344.42</td>
</tr>
<tr>
<td>217</td>
<td>Process Piping Labor</td>
<td>$69,588.64</td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>69,588.64</td>
</tr>
<tr>
<td>218</td>
<td>Valves Materials</td>
<td>$42,830.00</td>
<td></td>
<td>10,554.50</td>
<td>10,554.50</td>
<td>25%</td>
<td>32,275.50</td>
</tr>
<tr>
<td>219</td>
<td>Valves Labor</td>
<td>$26,450.68</td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>26,450.68</td>
</tr>
<tr>
<td>220</td>
<td>Insulation</td>
<td>$6,825.00</td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>6,825.00</td>
</tr>
<tr>
<td>221</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>222</td>
<td>Pollution Control Equipment</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>223</td>
<td>Vertical Turbine Pumps Materials</td>
<td>$115,300.00</td>
<td>102,700.00</td>
<td>112,600.00</td>
<td>215,300.00</td>
<td>187%</td>
<td>(100,000.00)</td>
</tr>
<tr>
<td>224</td>
<td>Vertical Turbine Pumps Labor</td>
<td>$24,601.24</td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>24,601.24</td>
</tr>
<tr>
<td>225</td>
<td>Slide Gates Materials</td>
<td>$24,155.00</td>
<td>18,116.25</td>
<td>6,038.75</td>
<td>24,155.00</td>
<td>100%</td>
<td></td>
</tr>
<tr>
<td>226</td>
<td>Slide Gates Labor</td>
<td>$9,001.40</td>
<td>4,500.70</td>
<td></td>
<td>4,500.70</td>
<td>50%</td>
<td>4,500.70</td>
</tr>
<tr>
<td>227</td>
<td>Clearwell Leak Testing</td>
<td>$18,144.00</td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>18,144.00</td>
</tr>
<tr>
<td>228</td>
<td>Lab Equipment</td>
<td>$7,216.00</td>
<td></td>
<td>7,216.00</td>
<td>7,216.00</td>
<td>100%</td>
<td></td>
</tr>
<tr>
<td>229</td>
<td>Filter Media Replacement Materials</td>
<td>$49,780.00</td>
<td>49,780.00</td>
<td></td>
<td>49,780.00</td>
<td>100%</td>
<td></td>
</tr>
<tr>
<td>230</td>
<td>Filter Media Replacement Labor</td>
<td>$16,480.00</td>
<td>16,480.00</td>
<td></td>
<td>16,480.00</td>
<td>100%</td>
<td></td>
</tr>
<tr>
<td>231</td>
<td>Forced Draft Aerator Materials</td>
<td>$125,890.00</td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>125,890.00</td>
</tr>
<tr>
<td>232</td>
<td>Forced Draft Aerator Labor</td>
<td>$14,995.00</td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>14,995.00</td>
</tr>
<tr>
<td>233</td>
<td>RO System Materials</td>
<td>$1,408,500.00</td>
<td>281,700.00</td>
<td>281,700.00</td>
<td>281,700.00</td>
<td>20%</td>
<td>1,126,800.00</td>
</tr>
<tr>
<td>234</td>
<td>RO System Labor</td>
<td>$203,600.00</td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>203,600.00</td>
</tr>
<tr>
<td>235</td>
<td>Chem Sys Chlorine Fluoride Caustic</td>
<td>$125,425.00</td>
<td></td>
<td>61,337.00</td>
<td>61,337.00</td>
<td>49%</td>
<td>64,088.00</td>
</tr>
<tr>
<td>236</td>
<td>Chem Systems Labor</td>
<td>$41,582.00</td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>41,582.00</td>
</tr>
<tr>
<td>237</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td colspan="2">Original Contract Totals</td>
<td>$12,182,553.00</td>
<td>$4,768,264.63</td>
<td>$736,298.89</td>
<td>$656,916.83</td>
<td>51%</td>
<td>$6,021,072.65</td>
</tr>
</table>
Sources
- revize: K.6 (lySlsD0sQFfxsF0YcAkb8lI6FtIY5i.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-6 Discussion and Consideration of Approval of State Revolving Fund (SRF) Reimbursement...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.