Text from the PDF text layer; check the PDF for anything that matters.PROJECT COST ESTIMATE
Tiffin Well 6
City of Tiffin, IA
MSA #136030XX
6/8/2026
ITEM ITEM ESTIMATED UNIT TOTAL
NO. DESCRIPTION QUANTITY UNITS COST COST
General
Mobilization, Bonds, and Insurance 1 LS $ 115,600 $ 115,600
Electrical and Fiber Service (From WTP to Wellhouse) 1 LS $ 70,000 $ 70,000
Wellhouse
Structural/ Architectural 1 LS $ 100,000 $ 100,000
HVAC 1 LS $ 10,000 $ 10,000
Electrical & Controls 1 LS $ 238,000 $ 238,000
Civil/ Site
Erosion and Sedimentation Control 1 LS $ 7,500 $ 7,500
Connect to Existing Watermain 1 EA $ 2,500 $ 2,500
6-inch D.I. Gate Valve 4 EA $ 2,500 $ 10,000
6-inch PVC Watermain 600 LF $ 75 $ 45,000
6-inch D.I. Watermain 40 LF $ 100 $ 4,000
Fire Hydrant Assembly 1 EA $ 6,000 $ 6,000
6-foot Chain Link Fence 240 LF $ 45 $ 10,800
Gravel Surfacing 900 SY $ 30 $ 27,000
Clearing and Grubbing 1 LS $ 5,000 $ 5,000
Seeding 2 AC $ 5,000 $ 10,000
Earthwork 1 LS $ 20,000 $ 20,000
18" RCP Culvert 32 LF $ 100 $ 3,200
Well Mechanical Components
Pitless Adapter Unit, Complete 1 LS $ 25,000 $ 25,000
30 HP Submersible Well Pump 1 LS $ 45,000 $ 45,000
4-inch Stainless Steel Column Pipe and Check Valves 280 VF $ 175 $ 49,000
Meter Pit 1 LS $ 25,000 $ 25,000
Acidizing 1 LS $ 40,000 $ 40,000
Test Pumping 24 HR $ 275 $ 6,600
Sampling and Testing 1 LS $ 7,500 $ 7,500
Chlorination 1 LS $ 3,500 $ 3,500
Construction Sub-Total $ 886,200
Construction Contingencies (20%) $ 177,240
Construction Subtotal $ 1,063,440
Legal $7,500
Engineering Design $84,000
Engineering Construction $84,000
Project Total Estimate $ 1,238,940
Sources
- revize: Attachment (qHKoDCqI6pg3JigLJQM5PrlpOWktXU.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: C Discussion to Investigate the potential output of Well #6 for Future Use
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.