I-4 - Engineer Statement of Final Completion - Original Town Urbanization Phase One
Page 1 of 1
Text read by the vision model; check the PDF for anything that matters.ENGINEER’S STATEMENT OF FINAL COMPLETION
AND
OWNER’S ACCEPTANCE OF THE WORK
PROJECT: Original Town Urbanization Phase One
OWNER: City of Tiffin, IA
ENGINEER: Hart-Frederick Consultants P.C.
CONTRACTOR: L.L. Pelling Co.
SURETY: Merchants Bonding Company (Mutual)
I, the undersigned Engineer of the above designated project, do hereby state that:
1) The construction provided for pursuant to CONTRACT DOCUMENTS including all approved amendments and Change Orders, hereafter called the Work between the OWNER and CONTRACTOR has been completed and to the best of my knowledge and belief, is in substantial compliance with the provisions of the CONTRACT DOCUMENTS.
2) The final payment authorized hereto and made a part hereof is a complete and accurate summary of the WORK performed in accordance with the CONTRACT DOCUMENTS.
3) The total cost of the WORK as completed is $1,310,233.78
I recommend, under the provisions of the CONTRACT DOCUMENTS, that the WORK be accepted and that the final payment be made.
Engineer
By ____________________________ Date 8 MARCH 2021
The CONTRACTOR shall guarantee materials and equipment furnished and construction performed under the PERFORMANCE & PAYMENT BOND, which shall remain in full force and effect for a period of three (3) years from the date of acceptance by OWNER.
Accepted by OWNER
By ____________________________ Title _______________________
Date of Acceptance: __________________________