contract agreement · K-4
K-4 - Pay Estimate 11 - Final - Original Town Urbanization Phase One - LL Pelling
Page 2 of 3
Text read by the vision model; check the PDF for anything that matters.PARTIAL PAYMENT ESTIMATE NUMBER 11 FINAL
CONTRACTOR: LL Pelling
ADDRESS: 1425 W. Penn St., PO Box230
CITY, STATE, ZIP North Liberty, IA 52317
OWNER: CITY OF TIFFIN
PROJECT: Original Town Urbanization Project: Phase One
HFC#12218.131
<table>
<tr>
<th>Date of Completion:</th>
<th>Amount of Contract:</th>
<th>Date of Estimate:</th>
</tr>
<tr>
<td>Original: 6/1/2019</td>
<td>Original: $1,082,008.00</td>
<td>From: 6-Nov-20</td>
</tr>
<tr>
<td>Revised:</td>
<td>Revised: $1,199,014.49 (C.O. #1-7)</td>
<td>To: 22-Feb-21</td>
</tr>
</table>
<table>
<tr>
<th></th>
<th>THIS PERIOD</th>
<th>TOTAL TO DATE</th>
</tr>
<tr>
<td>Amount Earned</td>
<td>$12,899.15</td>
<td>$1,310,233.78</td>
</tr>
<tr>
<td>Add Material Stored On-Site</td>
<td></td>
<td>$25,915.00</td>
</tr>
<tr>
<td>Subtract Materials Installed On-Site</td>
<td></td>
<td>$25,915.00</td>
</tr>
<tr>
<td>Subtotal</td>
<td>$12,899.15</td>
<td>$1,310,233.78</td>
</tr>
<tr>
<td>Retainage (5%)</td>
<td>-$64,866.75</td>
<td>$-</td>
</tr>
<tr>
<td>Previous Payments</td>
<td></td>
<td>$1,232,467.88</td>
</tr>
<tr>
<td>Amount Due</td>
<td>$77,765.90</td>
<td>$77,765.90</td>
</tr>
</table>
Estimated % of Job Complete Based on Amount Earned/Contract Amount only N/A
This does not constitute work completed to date
Is Contractor's Construction Progress on Schedule? YES NO N/A ✗
I hereby certify that I have carefully inspected the work and as a result of my inspection and to the best of my knowledge and belief, the quantities shown in this estimate are correct and have not been shown in previous estimates and the work has been performed in accordance with the contract documents.
HART-FREDERICK CONSULTANTS P.C.
By: [signature]
Title: Benjamin A. Carhoff, Project Engineer
Date: March 8, 2021
Approved by Owner's Representative:
By: ____________________________
Title: ____________________________
(Additional signatures -- if required)
By: ____________________________
Title: ____________________________
Sources
- sharepoint (K-4 - Pay Estimate 11 - Final - Original Town Urbanization Phase One - LL Pelling.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.