Text read by the vision model; check the PDF for anything that matters.STATEMENT OF COMPLETION AND FINAL ACCEPTANCE OF WORK
Contractor Vieth Construction Corp.
Work Type PCC Pavement - Grade and Replace
Accounting ID(s) 35177
Project Number(s) STP-U-7662(612)--70-52
Letting Date 4/17/2018
Contract ID 52-7662-612
Additional Comments
Type of Contract
[ ] Specified Start Date
[ ] Approximate Start Date
[x] Late Start Date 6/6/2018
[ ] Completion Date Contract
Actual Start Date 6/11/2018
Field Completion Date 8/24/2020
Site No.(s) 00
Working Days Specified: 104
Working Days Charged: 146
Closure Days Specified:
Closure Days Charged:
Recommended for Acceptance
Signature [signature]
Date 8 October 2020
Iowa DOT Contract Acceptance
Signature [blank]
Date [blank]
Approved and Work Accepted on Behalf of the Board of Supervisors of [blank] County this [blank] Day of [blank] Year
Signature [blank]
County Engineer
For Central Office Use Only
Recorded Finance [blank]
Recorded Construction & Materials [blank]
NOTE: On county administered projects, the County Engineer is required to sign "Recommended for Acceptance" and "Approved and Work Accepted on Behalf of the Board of Supervisors".
Sources
- sharepoint (I-2 - Resolution 2021-026 - Final Acceptance of Roberts Ferry Road Project.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.