I-3 - Resolution 2021-027 - Release Requirements of Lots 22 and 23 - Woodfield Ridge Part Six
Page 2 of 2
Text read by the vision model; check the PDF for anything that matters.SECOND AMENDMENT TO DEVELOPER'S AGREEMENT
WOODFIELD RIDGE -- PART SIX
THIS AGREEMENT, made by and between the CITY OF TIFFIN, IOWA, a municipal corporation, hereinafter referred to as "City," and QS DEVELOPMENT INC., hereinafter referred to as "Developer."
RECITALS
A. Hochstedler Building & Development LLC and the City of Tiffin, Iowa entered into a Developer’s Agreement Woodfield Ridge -- Parts Six and Seven (the “Developer’s Agreement”), dated December 6, 2016, with respect to the subdivision of 31.56 acres.
B. Hochstedler Building & Development LLC entered into an Assignment and Assumption Agreement with Developer and the City has consented to the assignment of the rights and obligations of Hochstedler Building and Development LLC to Developer and the assumption thereof by Developer.
C. An Amendment to Developer’s Agreement was executed by Developer and City in August of 2017.
D. The City and Developer have agreed to further amend the Developer’s Agreement.
NOW THEREFORE, the City and Developer agree as follows:
I. Lots 22 and 23. Section 3(C)(1) is amended by adding (i) as follows:
i. Lots 22 and 23 shall not be conveyed and no building permits will be issued until Ironwood Lane has been constructed and accepted by the City. Further, Lots 22 and 23 shall not have curb cuts or driveway access onto Croell Avenue.
II. No Other Modification. Except as expressly modified by this Second Amendment, and except as may be necessary to incorporate the changes effected by this Second