Text read by OCR; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades - City of Tiffin
Contract:
Application No.: 12R Application Period: From 07/24/26 to 08/21/26 Application Date: 08/21/26
211 Process Piping Materials $111,340.84 - 24,701.00 42,224.48 66,925.48 60% 44,415.36
212 Process Piping Labor $85,502.50 2,137.56 19,238.06 21,375.62 25% 64,126.88
213 Valves Materials $83,000.00 - 29,765.00 29,765.00 36% 53,235.00
214 Valves Labor $30,614.26 - - 0% 30,614.26
215 Structure 30 - Clearwell - - -
216 Process Piping Materials $62,822.42 7,658.00 6,259.50 2,820.00 16,737.50 27% 46,084.92
217 Process Piping Labor $69,588.64 - 17,397.16 17,397.16 25% 52,191.48
218 Valves Materials $42,830.00 - 10,554.50 10,554.50 25% 32,275.50
219 Valves Labor $26,450.68 - - 0% 26,450.68
220 Insulation $6,825.00 - - 0% 6,825.00
221 - = 2
222 Pollution Control Equipment - - -
223 Vertical Turbine Pumps Materials $115,300.00 2,700.00 112,600.00 115,300.00 100% -
224 Vertical Turbine Pumps Labor $24,601.24 - - 0% 24,601.24
225 Slide Gates Materials $24,155.00 24,155.00 24,155.00 100% -
226 Slide Gates Labor $9,001.40 9,001.40 9,001.40 100% -
227 Clearwell Leak Testing $18,144.00 - 18,144.00 18,144.00 100% -
228 Lab Equipment $7,216.00 - 7,216.00 7,216.00 100% -
229 Filter Media Replacement Materials $49 780.00 49,780.00 49,780.00 100% -
230 Filter Media Replacement Labor $16,480.00 16,480.00 16,480.00 100% -
231 Forced Draft Aerator Materials $125,890.00 - 31,472.50 31,472.50 62,945.00 50% 62,945.00
232 Forced Draft Aerator Labor $14,995.00 749.75 6,747.75 7,497.50 50% 7,497.50
233 RO System Materials $1,408, 500.00 281,700.00 915,525.00 1,197,225.00 85% 211,275.00
234 RO System Labor $203,600.00 - 162,880.00 162,880.00 80% 40,720.00
235 Chem Sys Chlorine Fluoride Caustic $125,425.00 = 125,425.00 125,425.00 100% -
236 Chem Systems Labor $41,582.00 4,158.20 4,158.20 10% 37,423.80
237 “ ~ =
Original Contract Totals| $ 12,182,553.00 | $ 6,640,343.04 | $1,910,282.04 801,479.18 |$ 9,352,104.26 77%| $ 2,830,448.74
EJCDC® C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved.
00 62 76-8o0f9 \\fileserver\Shares\Projects\Active\Tiffin WTP (25-012-IA)\3-Tricon\PaymentApplications\Pay Application
Sources
- revize: Agenda packet (packet_2026-09-01_3ad1ee37-4af1-4a67-8983-cc30e19b0f9e.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 18, 2026. Built from the archive's documents; see how the data is built.