PROJECT UPDATE
NORTH PARK ROAD IMPROVEMENTS – JAMES WATTERS
Work on the sanitary service for the property on the Southwest corner of North Park Road and Mopar Drive
has been completed and a change order has been processed.
The Oak Hill Elementary entrance was completed Friday, August 21st and was opened to public traffic the
following Monday morning for the start of the school year.
Roadway paving on both northbound and southbound lanes has been completed with hand-pours for
intersections, median, driveway, and tie-in paving remaining. Paving of sidewalk and trail is set to begin in
late August or early September.
Given the amount of anticipated traffic on North Park Road, is not expected that the roadway can be safely
opened to the public until construction activities causing traffic disruption can be minimized.
ROBERTS FERRY ROAD SHOULDER WIDENING – ANDREW INHELDER
MSA has surveyed the area and have begun preliminary design to widen the shoulder. We will present the
plans and opinion of cost to the City in September.
US 6 AND DEER VIEW AVE TRAFFIC SIGNAL DESIGN – JAMES WATTERS
The City is upgrading the temporary traffic signals at US 6 and Deer View Avenue to permanent signals. The
survey was delayed to allow topo collection for this intersection and the North Park Road intersection at
the same time. Survey work for both intersections has now been scheduled and will be completed shortly.
A kickoff meeting with the City will be held after the survey is completed. Traffic turning movement counts
are planned for September and October and will likely be used to support the design of the proposed
improvements. Trail and stormwater improvements are also anticipated as part of the overall design effort
in this area.
PROJECT UPDATE
Page 2 of 5
Sources
- revize: L-2 (U1iMGaOlVmnDPmjQmBUo7TUFEsBVNx.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-2 City Engineer's Report [AMENDED]
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.