engineering report · L-2
City Engineer's Report [AMENDED] — L-2
Page 1 of 5
Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISON:
Andrew Inhelder, PE
Office: 319.364.4773
Cell: 515.802.0906
[email protected]
DATE:
August 28, 2026
ON-GOING PROJECTS
REVERSE OSMOSIS WATER TREATMENT PLANT DESIGN – CLINT WIENEN
The RO skids have been delivered and assembled. Masonry walls within the RO building have been
completed and painted will be completed within the next couple of weeks. Driveway paving has been
partially completed. The Clearwell has been properly cleaned, disinfected, and tested for leaks. Work to
be completed in the next month includes metal siding and roofing, truss installation on the addition to the
existing treatment building, mezzanine construction, and ongoing electrical, plumbing, and HVAC items.
At the construction meeting held on 8/25/2026, Tricon Construction is not anticipating the RO System to
be operational until mid to late November. Substantial Completion was identified as 9/30/2026 in the
Agreement.
VILLAGE DRIVE & ROBERTS FERRY ROAD SIGNAL DESIGN – ANDREW INHELDER
Project was awarded to Neumiller Electric, Inc on May 19th, 2026. Contractor and MSA are working
through shop drawing submittal and review. The contractor has tentatively planned to begin construction
in September. A pre-construction meeting will be scheduled closer to the anticipated project start date.
Substantial Completion date for the project is October 2, 2026.
HIGHWAY 6 CONCEPT AND COST ESTIMATE – JAMES WATTERS
Final plans for letting were submitted to the DOT on August 4, 2026.The project will open bids for project
in mid-October
The DOT is currently working on the construction agreement with the City and will be submitting to the
City for signature when ready. This agreement will put in place construct cost splits between the City and
DOT.
PROJECT UPDATE
Page 1 of 5
Sources
- revize: L-2 (U1iMGaOlVmnDPmjQmBUo7TUFEsBVNx.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-2 City Engineer's Report [AMENDED]
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.