contract agreement · K-2

K-2 - Change Order 2 - Original Town Phase Two - Rathje Construction

Open the PDF Searchable (OCR) PDF

Page 2 of 2

Text read by the vision model; check the PDF for anything that matters.
Date: June 22, 2021 To: Ben Carhoff Project: Tiffin Original Town Urbanization Phase II Re: COR #2 Rathje # 7187 Ben, I am hereby submitting the following change order request for the 2 sump line connections at 221 Summer Hayes & 1 sump line connection at 211 Summer Hayes into intake I-23 as requested. If additional sump line connections are encountered going forward, this change order reflects the unit price. <table> <tr> <th>Item</th> <th>Description</th> <th>Qty</th> <th>Unit</th> <th>Unit Price</th> <th>MU</th> <th>Unit w/ MU</th> <th>Total</th> </tr> <tr> <td>Sump Line Connections</td> <td></td> <td>3.00</td> <td>EA</td> <td>$685.00</td> <td>0.00%</td> <td>$685.00</td> <td>$2,055.00</td> </tr> <tr> <td colspan="7">Total</td> <td>$2,055.00</td> </tr> </table> Please call if you have any questions. Respectfully, Dan Scofield

Sources

  • sharepoint (K-2 - Change Order 2 - Original Town Phase Two - Rathje Construction.pdf) — where it was found ↗ first seen Oct 12, 2026

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.