Text read by the vision model; check the PDF for anything that matters.Date: June 22, 2021
To: Ben Carhoff
Project: Tiffin Original Town Urbanization Phase II
Re: COR #2
Rathje # 7187
Ben,
I am hereby submitting the following change order request for the 2 sump line connections at 221 Summer Hayes & 1 sump line connection at 211 Summer Hayes into intake I-23 as requested. If additional sump line connections are encountered going forward, this change order reflects the unit price.
<table>
<tr>
<th>Item</th>
<th>Description</th>
<th>Qty</th>
<th>Unit</th>
<th>Unit Price</th>
<th>MU</th>
<th>Unit w/ MU</th>
<th>Total</th>
</tr>
<tr>
<td>Sump Line Connections</td>
<td></td>
<td>3.00</td>
<td>EA</td>
<td>$685.00</td>
<td>0.00%</td>
<td>$685.00</td>
<td>$2,055.00</td>
</tr>
<tr>
<td colspan="7">Total</td>
<td>$2,055.00</td>
</tr>
</table>
Please call if you have any questions.
Respectfully,
Dan Scofield