contract agreement · K-3
K-3 - Change Order 4 - Rathje - Original Town Phase Two
Page 2 of 2
Text read by the vision model; check the PDF for anything that matters.Date: August 11, 2021
To: Ben Carhoff
Project: Tiffin Original Town Urbanization Phase II
Re: COR #5R
Rathje # 7187
Ben,
I am hereby submitting the following change order request for the necessary effort to explore the water main layout in the 2nd Street and Main Street. This excavation was required to determine which lines of the distribution system was in operation. Incorrect Record Drawings from previous work and needed to investigate how the water system operated.
<table>
<tr>
<th>Item</th>
<th>Description</th>
<th>Qty</th>
<th>Unit</th>
<th>Unit Price</th>
<th>MU</th>
<th>Unit w/ MU</th>
<th>Total</th>
</tr>
<tr>
<td>Exploratory Excavation</td>
<td></td>
<td>1.00</td>
<td>LS</td>
<td>$5,283.08</td>
<td>0.00%</td>
<td>$5,283.08</td>
<td>$5,283.08</td>
</tr>
<tr>
<td colspan="7">Total</td>
<td>$5,283.08</td>
</tr>
</table>
Additional Day(s): 1.0
Please call if you have any questions.
Respectfully,
J. Shawn Lueth, PE
Sources
- sharepoint (K-3 - Change Order 4 - Rathje - Original Town Phase Two.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.