contract agreement · K-3
K-3 - Change Order 4 - Rathje - Original Town Phase Two
Page 1 of 2
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 11 August, 2021
Change Order No: 4 (Four)
Agreement Date: 5 May, 2020
PROJECT: Original Town Urbanization Project: Phase Two HFC#12218.13123
OWNER: City of Tiffin, IA
CONTRACTOR: Rathje Construction
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Exploratory Excavation to determine watermain location at the intersection of 2nd and Main Streets. As-built drawings of previous installation were incorrect. Price includes labor, equipment and materials.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $1,824,618.96
CONTRACT with LAST CHANGE ORDER: $1,817,587.46
THIS CHANGE ORDER AMOUNT: $5,283.08
NEW CONTRACT PRICE: $1,822,870.54
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): 1 day
NEW Completion Date: 2 June, 2022
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER:
CONTRACTOR: See Attached
ENGINEER: