Text read by the vision model; check the PDF for anything that matters.From: [email protected] on behalf of Alex Weber <[email protected]>
Sent: Tuesday, September 14, 2021 1:23 PM
To: Benjamin A. Carhoff
Subject: Asphalt Pricing
Ben,
Here's the pricing for placing the Asphalt:
7 Tons Asphalt @ $114/Ton= $798
Mini Excavator: 5 HRS @ $145/ Hr = $725
Foreman: 5 Hrs @ $65/HR= $325
Laborer: 5 Hrs @ 58/HR= $290
Total: $2,138.00
- This doesn't include a half day for railroad flaggers. Tom mentioned you thought that the city is paying for that, but when I read the spec to me it says its the contractors responsibility. So that would have to be added if we end up with the bill. We would also like a working day added to the completion date.
Thanks,
Alex
--
Alex Weber
Vieth Construction Corporation
6419 Nordic Dr. Cedar Falls Ia 50613
Ph- 319-277-1006
Fax- 319-277-3383
Cell- 319-404-4506
Sources
- sharepoint (K-4 - Change Order #1 - Vieth Construction - Trail Phase 6.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.