contract agreement · K-4
K-4 - Change Order #1 - Vieth Construction - Trail Phase 6
Page 1 of 2
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER#
DATE: 10/12/2021
Change Order No: 1 (ONE)
Agreement Date: 4/20/2021
PROJECT: TAP-U-7662(614)—8I-52 Tiffin Trial Phase 6
OWNER: City of Tiffin, IA
CONTRACTOR: Vieth Construction Corp.
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Asphalt placed at the railroad crossing during the original install did not allow for concrete trail to be placed in accordance with ADA regulations. A decision was made to stop thee concrete work at the at the same distance from the crossing as the roadway pavement and place asphalt to connect to the original crossing pavement.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $ 89,588.50
CONTRACT with LAST CHANGE ORDER: $89,588.50
THIS CHANGE ORDER AMOUNT: $2,138.00
NEW CONTRACT PRICE: $ 91,726.50
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): 1 day
NEW Completion Date: 1 October, 2021
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER: ________________________________
CONTRACTOR: See attached email
ENGINEER: ________________________________