K-4 - Change Order 9 - Rathje Construction, Original Town Phase Two

Open the PDF Searchable (OCR) PDF

Page 1 of 2

Text read by the vision model; check the PDF for anything that matters.
CHANGE ORDER DATE: 8 November, 2021 Change Order No: 9 (Nine) Agreement Date: 5 May, 2020 PROJECT: Original Town Urbanization Project: Phase Two HFC#12218.13123 OWNER: City of Tiffin, IA CONTRACTOR: Rathje Construction DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS: Installation of roof drain and sump pump connections. See attached COR #10. CONTRACT PRICE CHANGES: Original CONTRACT PRICE: $1,824,618.96 CONTRACT with LAST CHANGE ORDER: $1,864,770.54 THIS CHANGE ORDER AMOUNT: $1,425.00 NEW CONTRACT PRICE: $1,866,195.54 CONTRACT TIME CHANGES CONTRACT TIME (increased)(decreased): ____________________________ NEW Completion Date: _________________________________________ APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER. OWNER: _______________________________________________________ CONTRACTOR: See Attached COR#10 ENGINEER: ___________________________________________________

Sources

  • sharepoint (K-4 - Change Order 9 - Rathje Construction, Original Town Phase Two.pdf) — where it was found ↗ first seen Oct 12, 2026

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.