• Neumiller Electric’s subcontractor was onsite Tuesday to begin installing traffic control
and erosion control measures, with underground construction expected to begin
immediately thereafter. This phase of the project is anticipated to take approximately
three to four weeks. The underground work will include installation of the wiring, minor
grading, pavement and sidewalk work, pole bases, and seeding of the site. Once this
work is completed, the contractor will demobilize from the site while waiting on the
delivery of the poles and mast arms. The poles are currently expected to be delivered in
approximately two months. Once the poles and mast arms arrive, the contractor will
return to complete installation and proceed with startup of the traffic signals.
• Work continues to progress on the Forevergreen Road and Jasper Avenue Improvements
Project. The contractor is currently working on installing the watermain section that is
on the Tiffin side of the project. They have begun to pour the intakes and intake throats
on the north leg of the roundabout.
• The block walls for the restroom project at Deer View Park have been completed. The
next step of the project is for the roof to be constructed. We still anticipate this project
being completed yet this fall but depending on the temperatures, full usage of the facility
might end up being next spring.
• Cade Prior, an Eagle Scout candidate from Clear Creek Amana, will be completing the
majority of his Eagle Scout project this weekend. Cade first presented his ‘Tiffin
Canopy Project’ to the City Council approximately one year ago, with the goal of further
beautifying the community by adding 100 trees throughout Tiffin. Working in
partnership with Forevergreen Nursery, Cade successfully sold all 100 trees. On Friday,
September 11, the Public Works Department will transport the trees from the nursery to
the Green Shed at the Auxiliary Park, which will serve as the tree pickup location.
Residents who purchased trees will pick them up on Saturday, September 12, from
9:00 a.m. to 12:00 p.m. Cade has done an outstanding job organizing and completing
this project, and his efforts will make a lasting contribution to the Tiffin community.
Sources
- revize: M-10 (CklBSKzX0yfhCfQPazqXN6gdXtvSyZ.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: M Reports from City Personnel
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.