K-3 - Change Order 14, Rathje Construction - Original Town Phase Two
Page 1 of 2
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 4 February, 2022
Change Order No: 14 (fourteen)
Agreement Date: 5 May, 2020
PROJECT: Original Town Urbanization Project: Phase Two HFC#12218.13123
OWNER: City of Tiffin, IA
CONTRACTOR: Rathje Construction
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
The Fire Department requested the relocation of the street light pole so it is not damaged by Fire Department equipment when leaving for an emergency call. The Fire Department also requested a thicker driveway slab with staged construction which incurred additional costs to the contractor. Cold weather protection of the concrete is also included in this change order. See attached COR #15 for additional information.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $1,824,618.96
CONTRACT with LAST CHANGE ORDER: $1,880,206.44
THIS CHANGE ORDER AMOUNT: $24,911.80
NEW CONTRACT PRICE: $1,905,118.24
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): No change
NEW Completion Date: ____________________________
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER: _______________________________________
CONTRACTOR: See Attached COR#15
ENGINEER: ____________________________________