K-4 - Change Order 15, Rathje Construction - Original Town Phase Two
Page 1 of 3
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 8 February, 2022
Change Order No: 15 (fifteen)
Agreement Date: 5 May, 2020
PROJECT: Original Town Urbanization Project: Phase Two HFC#12218.13123
OWNER: City of Tiffin, IA
CONTRACTOR: Rathje Construction
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
This change order is for the purchase of brick pavers to be used in Phase 3 of the project to ensure continuity of paver color and texture. City will provide storage area for 83 pallets of brick pavers.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $ 1,824,618.96
CONTRACT with LAST CHANGE ORDER: $ 1,905,118.24
THIS CHANGE ORDER AMOUNT: $ 46,285.84
NEW CONTRACT PRICE: $ 1,951,404.08
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): No change
NEW Completion Date:
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER:
CONTRACTOR: See Attached COR#16
ENGINEER: