K-3 - Change Order 1 - Shawver Well Company - Well 5 Improvements
Page 1 of 1
Text from the PDF text layer; check the PDF for anything that matters.February 24, 2022 CHANGE ORDER NO. 1
WELL 5 IMPROVEMENTS
TIFFIN, IOWA
Change Order No. 1 is for the following modifications to the project:
1. Delete Bid Item 1.1.4 Drill Hole 12.25 80 LF @ $85/LF $(6,800.00)
2. Delete Bid Item 2.1.4 Drill Hole 12.25 80 LF @ $85/LF $(6,800.00)
3. Additional labor, equipment and materials to drill 14.75" hole
for Test Well 5A. 80 LF @ $102/LF $ 8160.00
3. Additional labor, equipment and materials to drill 14.75" hole
for Test Well 5B. 80 LF @ $102/LF $ 8160.00
Total: $ 2,720.00
Change Order No. 1 increases the contract amount by $ 2,720.00 .
SHAWVER WELL COMPANY, INC. CITY OF TIFFIN, IOWA
By By
Title Title
Date Date
VEENSTRA & KIMM, INC. ATTEST:
By By
Title Project Engineer Title
Date February 24, 2022 Date
V&K Job No. 5093