Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 4/21/2022
Change Order No: 2 (TWO)
Agreement Date: 12/15/2020
PROJECT: Permeable Paver Parking Project HFC#15218.205
OWNER: City of Tiffin, IA
CONTRACTOR: Nolan's Lawn Care
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Due to staff turnover incorrect quantities were included in the bidding documents. Corrections per invoice quantities are as follows:
<table>
<tr>
<th>Item #</th>
<th>Description</th>
<th>Quantity</th>
<th>Unit</th>
<th>Rate</th>
<th>Total</th>
</tr>
<tr>
<td>104</td>
<td>Filter Layer IDOT Grad #3, Class 2</td>
<td>251.80</td>
<td>CY</td>
<td>$34.00</td>
<td>$8,561.20</td>
</tr>
<tr>
<td>105</td>
<td>Subbase Layer IDOT Grad #13</td>
<td>153.43</td>
<td>TON</td>
<td>$20.00</td>
<td>$3,068.60</td>
</tr>
<tr>
<td>109</td>
<td>Modified Subbase</td>
<td>1847.36</td>
<td>SY</td>
<td>$34.00</td>
<td>$62,810.24</td>
</tr>
<tr>
<td>110</td>
<td>Impermeable Membrane ....</td>
<td>253.83</td>
<td>SY</td>
<td>$4.00</td>
<td>$1,015.32</td>
</tr>
<tr>
<td>201</td>
<td>Furnish & Inst...Perm. Pavers</td>
<td>9.00</td>
<td>SY</td>
<td>$50.85</td>
<td>$457.65</td>
</tr>
<tr>
<td>206</td>
<td>8" Perforated Subdrain</td>
<td>-241.00</td>
<td>LF</td>
<td>$10.00</td>
<td>-$2,410.00</td>
</tr>
<tr>
<td>210</td>
<td>Modified Subbase</td>
<td>553.00</td>
<td>SY</td>
<td>$33.00</td>
<td>$18,249.00</td>
</tr>
<tr>
<td>211</td>
<td>Impermeable Membrane ....</td>
<td>90.64</td>
<td>SY</td>
<td>$400</td>
<td>$354.68</td>
</tr>
<tr>
<td colspan="5">Total</td>
<td>$92,106.69</td>
</tr>
</table>
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $295,124.66
CONTRACT with LAST CHANGE ORDER: $
THIS CHANGE ORDER AMOUNT: $92,106.69
NEW CONTRACT PRICE: $387,231.35
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased):
NEW Completion Date:
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER:
CONTRACTOR:
ENGINEER: