contract agreement · K-3
K-3 - Pay Application 3 - Woodruff Construction - PW Building
Page 2 of 3
Text read by the vision model; check the PDF for anything that matters.APPLICATION AND CERTIFICATION FOR PAYMENT
TO OWNER REPRESENTATIVE: City of Tiffin
PROJECT: Tiffin Public Works Building
FROM CONTRACTOR: Woodruff Construction
501 Greenfield Drive
Tiffin, IA 52340
ARCH / ENG: Martin Gardner Architecture
700 11th St. Suite 200
Marion, IA 52302
APPLICATION NO: 3
PERIOD TO: 04/30/22
PROJECT #: 22-005
CONTRACT #:
ORDER #:
REQ / REF #:
CONTRACTOR'S APPLICATION FOR PAYMENT
Application is made for payment, as shown below, in connection with the Contract. Continuation Sheet, AIA Document G703, is attached.
<table>
<tr>
<th>ORIGINAL CONTRACT SUM</th>
<td>$ 2,552,000.00</td>
</tr>
<tr>
<th>Net change by Change Orders</th>
<td>$ 0.00</td>
</tr>
<tr>
<th>CONTRACT SUM TO DATE (Line 1 ± 2)</th>
<td>$ 2,552,000.00</td>
</tr>
<tr>
<th>TOTAL COMPLETED & STORED TO DATE (Column G on G703)</th>
<td>$ 360,153.18</td>
</tr>
<tr>
<th>RETAINAGE:</th>
<td></td>
</tr>
<tr>
<td>a. 5% of Completed Work (Column D + E on G703)</td>
<td>$ 15,959.00</td>
</tr>
<tr>
<td>b. 5% of Stored Material (Column F on G703)</td>
<td>$ 2,048.66</td>
</tr>
<tr>
<td>Total Retainage (Lines 5a + 5b or Total in Column I of G703)</td>
<td>$ 18,007.66</td>
</tr>
<tr>
<th>TOTAL EARNED LESS RETAINAGE (Line 4 Less Line 5 Total)</th>
<td>$ 342,145.52</td>
</tr>
<tr>
<th>LESS PREVIOUS CERTIFICATES FOR PAYMENT (Line 6 from prior Certificate)</th>
<td>$ 183,183.75</td>
</tr>
<tr>
<th>CURRENT PAYMENT DUE</th>
<td>$ 158,961.77</td>
</tr>
<tr>
<th>BALANCE TO FINISH, INCL RETAINAGE (Line 3 less Line 6)</th>
<td>$ 2,209,854.48</td>
</tr>
</table>
<table>
<tr>
<th>CHANGE ORDER SUMMARY</th>
<th>ADDITIONS</th>
<th>DEDUCTIONS</th>
</tr>
<tr>
<td>Total changes approved in previous months by Owner</td>
<td></td>
<td></td>
</tr>
<tr>
<td>Total approved this Month</td>
<td></td>
<td></td>
</tr>
<tr>
<th>TOTALS</th>
<th>$0.00</th>
<th>$0.00</th>
</tr>
<tr>
<th>NET CHANGES by Change Order</th>
<th colspan="2">$0.00</th>
</tr>
</table>
The undersigned Contractor certifies that to the best of the Contractor's knowledge, information and belief the Work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for Work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.
CONTRACTOR:
By: [signature]
Date: 5-2-2022
State of: Iowa
County of: Johnson
Subscribed and sworn to before me this 2 day of May 2022
Notary Public: DANA ARNDT
My Commission Expires: January 13, 2024
ARCHITECT'S CERTIFICATE FOR PAYMENT
In accordance with the Contract Documents, based on on-site observations and the data comprising the application, the Architect certifies to the Owner that to the best of the Architect's knowledge, information and belief the Work has progressed as indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractor is entitled to payment of the AMOUNT CERTIFIED.
AMOUNT CERTIFIED .......... $ 158,961.77
(Attach explanation if amount certified differs from the amount applied. Initial all figures on this Application and on the Continuation Sheet that are changed to conform with the amount certified.)
ARCHITECT: MARTIN GARDNER ARCHITECTURE
By: Sarah M. Coleman Date: 5.4.2022
This Certificate is not negotiable. The AMOUNT CERTIFIED is payable only to the Contractor named herein. Issuance, payment and acceptance of payment are without prejudice to any rights of the Owner or Contractor under this Contract.