resolution · H-1
Resolution No. 2026-047 A Resolution Approving the Iowa Statewide Transportation Alternatives Set-Aside Program (TA Set-Aside) Application — H-1
Page 8 of 35
Text from the PDF text layer; check the PDF for anything that matters. |4
Amount: Source:
Funds are: Secured ☐ Anticipated: ☐ Funds are: Federal: ☐ State: ☐ Local: ☐ Private: ☐
Intended use of these funds:
Conditions on the use of funds:
Amount: Source:
Funds are: Secured ☐ Anticipated: ☐ Funds are: Federal: ☐ State: ☐ Local: ☐ Private: ☐
Intended use of these funds:
Conditions on the use of funds:
PART D – PROJECT DEVELOPMENT MILESTONES
Please provide a timeline of your project milestones below. For a construction project (or as applicable), estimated
dates should be identified for major milestones such as: submittal of a concept statement, anticipated NEPA
clearance, initiation of preliminary design, acquisition of right-of-way, completion of final design, planned project
letting date, start of construction, estimated construction completion date, completion of a final construction audit,
and when final closure of the project is expected. Add any additional milestones as appropriate for your project.
Projects will be required to be let within two years of funds being available (programmed in the TIP/STIP) to the
project. Upon award and execution of a project funding agreement, projects that fail to make satisfactory progress
may be terminated by Iowa DOT.
DATE PROJECT MILESTONE
January 2027 Notice of Award
February 2027 Funding Agreement
March 16, 2027 Concept Statement Submitted to IaDOT Local Systems Bureau
September 14, 2027 Preliminary Plans to IaDOT Local Systems Bureau
October 2027 Public Involvement Meeting
October 2027 NEPA Clearance Complete, Begin ROW Acquisition
November 2, 2027 Check Plans to IaDOT Local Systems Bureau
December 21, 2027 Final Plans to IaDOT Local Systems Bureau
March 21, 2028 Target Letting Date
May, 2028 Start of Construction
October 202 Completion of Construction
June 2029 Final Closure of Project
PART E – SAFE ROUTES TO SCHOOL PROJECT INFORMATION (ONLY IF APPLICABLE)
This section is only required to be completed if requesting funding for a Safe Routes to School project.
Survey data collected. A Safe Routes to School project is required to have completed the necessary planning and
preparation activities including collecting data about the school(s) and student population. Please see
http://saferoutesdata.org for forms, tips, and instructions. Please DO NOT provide your survey forms with this
application.
Sources
- revize: H-1 (qqh90ssRBjM0YMSB9978GDhkmHl9AG.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: H-1 Resolution No. 2026-047 A Resolution Approving the Iowa Statewide Transportation...