Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
July 5, 2022
PROJECT UPDATE
Deer View Avenue and Tall DOT has requested concurrence from the City on permanent TBD
Grass Avenue & Hwy 6 improvements to intersection within 5 years of installation of
Intersection Improvements temporary traffic signals in 2020. Scope includes both
pedestrian and vehicle accommodations.
Highway 6 Concept and Cost Estimate
The Iowa DOT provided MSA updated traffic projections for US 6 on June 14, 2022. The Iowa DOT has
completed their review on June 22, 2022 of the Prairie Valley Development Traffic Impact Study with
comments. ORGIN design will need to address those comments. With this information, MSA is moving forward
with traffic analysis and concept development for this project.
Preliminary Water and Wastewater Evaluation
A Task Order to review flows and loadings, wastewater and water treatment alternatives, budgetary cost
estimating, and coordinate with the DNR on the City’s chloride compliance schedule was submitted and
executed on May 9, 2022. The City has provided MSA with several documents including as-built plans and
operations manual. This information is being used to complete the evaluations.
DEVELOPMENT ASSISTANCE
Planning & Zoning (P&Z)
No update.
Shamrock Center Lot 5 Site Plan
Developer’s engineer submitted site plans to the City for review. MSA has reviewed and provided comments
to the developer’s engineer.
Park Place Part 8
Developer’s engineer provided responses to previous MSA review comments along with revised plans.
Additional comments were submitted to developer’s engineer.
PROJECT UPDATE
Page 2 of 2
Sources
- sharepoint (M-6 - City Engineer Report.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.