other · M-8
M-8 - Tiffin Well Schedule 2023
Page 1 of 1
Text read by the vision model; check the PDF for anything that matters.<table>
<tr>
<th>ID</th>
<th>Task Mode</th>
<th>Task Name</th>
<th>Duration</th>
<th>Start</th>
<th>Finish</th>
<th>Predecessors</th>
<th>Resource Names</th>
</tr>
<tr>
<td>1</td>
<td></td>
<td>Milestone 1</td>
<td>194 days?</td>
<td>Mon 8/29/22</td>
<td>Fri 6/2/23</td>
<td></td>
<td></td>
</tr>
<tr>
<td>2</td>
<td>✔️</td>
<td>Notice of Award</td>
<td>1 day</td>
<td>Tue 8/23/22</td>
<td>Tue 8/23/22</td>
<td></td>
<td></td>
</tr>
<tr>
<td>3</td>
<td>✔️</td>
<td>Install Traffic Control</td>
<td>1 day</td>
<td>Mon 1/23/23</td>
<td>Mon 1/23/23</td>
<td></td>
<td>Dirt</td>
</tr>
<tr>
<td>4</td>
<td>✔️</td>
<td>Construction Entrance</td>
<td>2 days</td>
<td>Mon 1/23/23</td>
<td>Tue 1/24/23</td>
<td>3SS</td>
<td>Dirt</td>
</tr>
<tr>
<td>5</td>
<td>✔️</td>
<td>Erosion Control</td>
<td>3 days</td>
<td>Fri 1/20/23</td>
<td>Tue 1/24/23</td>
<td></td>
<td>Zippy</td>
</tr>
<tr>
<td>6</td>
<td>✔️</td>
<td>Clearing and Grubbing</td>
<td>3 days</td>
<td>Wed 1/25/23</td>
<td>Fri 1/27/23</td>
<td>5</td>
<td>Dirt</td>
</tr>
<tr>
<td>7</td>
<td>✔️</td>
<td>Install Watermain</td>
<td>3.6 wks</td>
<td>Mon 1/23/23</td>
<td>Fri 2/17/23</td>
<td>5</td>
<td>Pipe</td>
</tr>
<tr>
<td>8</td>
<td>✔️</td>
<td>Company Safety Training - No Site Work 1 wk</td>
<td>1 wk</td>
<td>Mon 2/20/23</td>
<td>Fri 2/24/23</td>
<td></td>
<td>All Crews</td>
</tr>
<tr>
<td>9</td>
<td>✔️</td>
<td>Install Pitless Unit</td>
<td>2 days</td>
<td>Mon 2/27/23</td>
<td>Tue 2/28/23</td>
<td></td>
<td>Cahoy</td>
</tr>
<tr>
<td>10</td>
<td>✔️</td>
<td>Install Meter Pit</td>
<td>2 wks</td>
<td>Mon 2/27/23</td>
<td>Fri 3/10/23</td>
<td>8</td>
<td>Pipe</td>
</tr>
<tr>
<td>11</td>
<td>✔️</td>
<td>Install Well Pump and Equipment</td>
<td>1 wk</td>
<td>Mon 3/13/23</td>
<td>Fri 3/17/23</td>
<td>10</td>
<td>Cahoy</td>
</tr>
<tr>
<td>12</td>
<td>✔️</td>
<td>Install Electrical Conduits and Wiring</td>
<td>2 wks</td>
<td>Mon 3/20/23</td>
<td>Fri 3/31/23</td>
<td>11</td>
<td>Price</td>
</tr>
<tr>
<td>13</td>
<td>✔️</td>
<td>Programming and Controls Integration</td>
<td>2 wks</td>
<td>Mon 4/3/23</td>
<td>Fri 4/14/23</td>
<td>12</td>
<td>Price</td>
</tr>
<tr>
<td>14</td>
<td>✔️</td>
<td>Grading, and Steework</td>
<td>1 wk</td>
<td>Mon 4/17/23</td>
<td>Fri 4/21/23</td>
<td>13</td>
<td>Dirt</td>
</tr>
<tr>
<td>15</td>
<td>✔️</td>
<td>Controls Integration</td>
<td>3 wks</td>
<td>Mon 4/24/23</td>
<td>Fri 5/12/23</td>
<td>14</td>
<td>Price</td>
</tr>
<tr>
<td>16</td>
<td>✔️</td>
<td>Test Operation of Well</td>
<td>2 wks</td>
<td>Mon 5/15/23</td>
<td>Fri 5/26/23</td>
<td>15</td>
<td>Price</td>
</tr>