contract agreement · K-3

K-3 - Pay Estimate 2 - Boomerang - Well 5 Pump, Controls and Watermain

Open the PDF

Page 2 of 2

Text from the PDF text layer; check the PDF for anything that matters.
SUMMARY Total Approved Total Completed Contract Price $ 779,550.00 $ 301,258.50 Approved Change Order (list each) Change Order No. 1 $ 8,052.88 $ - Change Order No. 2 $ 9,081.57 $ 8,342.00 Revised Contract Price $ 796,684.45 $ 309,600.50 Stored $ 50,372.70 Total Earned $ 359,973.20 Retainage (5%) $ 17,998.66 Total Earned Less Retainage $ 341,974.54 Total Previously Approved (list each) Pay Estimate No. 1 $ 210,331.14 Total Previously Approved $ 210,331.14 Percent Complete 39% Amount Due This Request $ 131,643.40 The amount $131,643.40 is recommended for approval for payment in accordance with the terms of the contract. Prepared By: Recommended By: Approved By: Boomerang Corp. Veenstra & Kimm, Inc. Tiffin, Iowa Signature: Keegan Parizek Signature: Signature: Name: Keegan Parizek Name: Dave Schechinger Name: Title: Project Manager Title: Engineer Title: Date: 03/02/2023 Date: March 2, 2023 Date: V&K Job No. 5093/1 2 of 2

Sources

  • sharepoint (K-3 - Pay Estimate 2 - Boomerang - Well 5 Pump, Controls and Watermain.pdf) — where it was found ↗ first seen Oct 12, 2026

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.