contract agreement · K-3
K-3 - Pay Estimate 2 - Boomerang - Well 5 Pump, Controls and Watermain
Page 2 of 2
Text from the PDF text layer; check the PDF for anything that matters. SUMMARY
Total Approved Total Completed
Contract Price $ 779,550.00 $ 301,258.50
Approved Change Order (list each) Change Order No. 1 $ 8,052.88 $ -
Change Order No. 2 $ 9,081.57 $ 8,342.00
Revised Contract Price $ 796,684.45 $ 309,600.50
Stored $ 50,372.70
Total Earned $ 359,973.20
Retainage (5%) $ 17,998.66
Total Earned Less Retainage $ 341,974.54
Total Previously Approved (list each) Pay Estimate No. 1 $ 210,331.14
Total Previously Approved $ 210,331.14
Percent Complete 39% Amount Due This Request $ 131,643.40
The amount $131,643.40 is recommended for approval for payment in accordance with the terms of the contract.
Prepared By: Recommended By: Approved By:
Boomerang Corp. Veenstra & Kimm, Inc. Tiffin, Iowa
Signature: Keegan Parizek Signature: Signature:
Name: Keegan Parizek Name: Dave Schechinger Name:
Title: Project Manager Title: Engineer Title:
Date: 03/02/2023 Date: March 2, 2023 Date:
V&K Job No. 5093/1 2 of 2