contract agreement · K-2
K-2 - Pay Estimate 3 - Boomerang - Well 5 Pump, Controls, Watermain
Page 2 of 2
Text from the PDF text layer; check the PDF for anything that matters. SUMMARY
Total Approved Total Completed
Contract Price $ 779,550.00 $ 635,958.50
Approved Change Order (list each) Change Order No. 1 $ 8,052.88 $ -
Change Order No. 2 $ 9,081.57 $ 8,342.00
Revised Contract Price $ 796,684.45 $ 644,300.50
Stored $ -
Total Earned $ 644,300.50
Retainage (5%) $ 32,215.03
Total Earned Less Retainage $ 612,085.47
Total Previously Approved (list each) Pay Estimate No. 1 $ 210,331.14
Pay Estimate No. 2 $ 131,643.40
Total Previously Approved $ 341,974.54
Percent Complete 81% Amount Due This Request $ 270,110.93
The amount $270,110.93 is recommended for approval for payment in accordance with the terms of the contract.
Prepared By: Recommended By: Approved By:
Boomerang Corp. Veenstra & Kimm, Inc. Tiffin, Iowa
Signature: Keegan Parizek Signature: Signature:
Name: Keegan Parizek Name: Dave Schechinger Name:
Title: Project Manager Title: Engineer Title:
Date: 03/25/2023 Date: March 24, 2023 Date:
V&K Job No. 5093/1 2 of 2