SUMMARY Total Approved Total Completed Contract Price $ 779,550.00 $ 635,958.50 Approved Change Order (list each) Change Order No. 1 $ 8,052.88 $ - Change Order No. 2 $ 9,081.57 $ 8,342.00 Revised Contract Price $ 796,684.45 $ 644,300.50 Stored $ - Total Earned $ 644,300.50 Retainage (5%) $ 32,215.03 Total Earned Less Retainage $ 612,085.47 Total Previously Approved (list each) Pay Estimate No. 1 $ 210,331.14 Pay Estimate No. 2 $ 131,643.40 Total Previously Approved $ 341,974.54 Percent Complete 81% Amount Due This Request $ 270,110.93 The amount $270,110.93 is recommended for approval for payment in accordance with the terms of the contract. Prepared By: Recommended By: Approved By: Boomerang Corp. Veenstra & Kimm, Inc. Tiffin, Iowa Signature: Keegan Parizek Signature: Signature: Name: Keegan Parizek Name: Dave Schechinger Name: Title: Project Manager Title: Engineer Title: Date: 03/25/2023 Date: March 24, 2023 Date: V&K Job No. 5093/1 2 of 2

Sources

  • sharepoint (K-2 - Pay Estimate 3 - Boomerang - Well 5 Pump, Controls, Watermain.pdf) — where it was found ↗ first seen Oct 12, 2026

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.