engineering report · M-6
M-6 - Engineer's Report
Page 3 of 3
Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
March 3, 2023
PROJECT UPDATE
Upcoming Projects
A summary of major upcoming infrastructure projects is listed below.
Major Upcoming Description Next Steps/Schedule
Infrastructure Project
Wastewater Treatment Improvements The current wastewater treatment facility (WWTF) has a Final Compliance with NPDES
chloride compliance schedule. There is not any wastewater Permit required October 1, 2025.
treatment equipment/processes designed to remove chloride
so typically source control is the only economical means of MSA presented its findings on
meeting compliance. The existing treatment facility is at about November 1st. MSA has
50% capacity. However, if the past growth rate continues an prepared a proposed schedule
expansion will be required in the next 6-8 years. for wastewater treatment, water
treatment and water supply
improvement projects.
Deer View Avenue and Tall Grass DOT has requested concurrence from the City on permanent TBD
Avenue & Hwy 6 Intersection improvements to intersection within 5 years of installation of
Improvements temporary traffic signals in 2020. Scope includes both
pedestrian and vehicle accommodations.
PROJECT UPDATE
Page 3 of 3