Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
April 27, 2023
PROJECT UPDATE
DEVELOPMENT ASSISTANCE
Lotus Hill OPD & The State OPD
MSA and City staff met with the development team on April 3rd to discuss various aspects of both developments
as it relates to impacts to traffic on and along Croell Avenue. Revised plans for both developments were
submitted on 4/26/2023 and are currently being reviewed.
Daytona Estates OPD
Revised plans were submitted on 4/17/2023. Review comments have been prepared and were sent to the
developer’s engineer on 4/27/2023.
Park Place Part 8
Construction on this residential development is on-going. MSA is providing weekly project update reports to
city staff.
Shamrock Center, Lot 1 & Lot 2
MSA completed its review of these site plans.
Little Clippers Day Care
MSA received the site plan on 2/22/2023. Initial review is complete, however, additional information was
requested from the developer’s engineer. Site plans were received on 3/31/2023. Comments were provided
on 4/6/2023.
Hawk Wash
No further reviews are required at this time.
Tiffin West Development
MSA received revised plat and drainage calculations on 3/30/2023. Comments were provided on 4/7/2023.
Upcoming Projects
Major Upcoming Description Next Steps/Schedule
Infrastructure Project
Wastewater Treatment Improvements The current wastewater treatment facility (WWTF) has a Final Compliance with NPDES
chloride compliance schedule. There is not any wastewater Permit required October 1, 2025.
treatment equipment/processes designed to remove chloride
so typically source control is the only economical means of MSA presented its findings on
meeting compliance. The existing treatment facility is at about November 1st. MSA has
50% capacity. However, if the past growth rate continues an prepared a proposed schedule
expansion will be required in the next 6-8 years. for wastewater treatment, water
treatment and water supply
improvement projects.
Deer View Avenue and Tall Grass DOT has requested concurrence from the City on permanent TBD
Avenue & Hwy 6 Intersection improvements to intersection within 5 years of installation of
Improvements temporary traffic signals in 2020. Scope includes both
pedestrian and vehicle accommodations.
PROJECT UPDATE