Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISONS:
Kevin Bailey, PE / Jake Huck, P.E.
Office: 319.364.4773
Cell(s): 319.855.8392/ 563.542.6571
[email protected] / [email protected]
DATE:
April 27, 2023
ON-GOING PROJECTS
North Park Road Improvements
The Concept Statement was submitted to the IowaDOT on 3/21/2023. In order to complete the environmental
review, the Office of the State Archaeologist is requiring a Phase I Archaeological survey be completed. An
agreement was executed with the City for Rolling Hills Consulting Services, LLC to provide the Phase I Survey.
MSA & city staff met with the developer for land west of and adjacent to North Park Road. The purpose of the
meeting was to discuss potential access requirements for future development in this area. Several options
were discussed and considered. MSA staff will present a project update to the council during the May 16th
work session. At this work session, members of the design team will discuss potential access improvements
with the council.
Highway 6 Concept and Cost Estimate
A planning meeting was held on 4/13/2023 with city staff, IowaDOT and MSA to discuss U.S. Hwy 6 planning
efforts. The funding source from the DOT is now for a full construction pushing construction out to possibly
2027. Also, MSA will be performing additional design for storm water conveyances, roadway rural section and
urban section design and subsequent impacts to right-of-way, and culvert extension improvements along this
section of Hwy 6. These designs and resulting cost estimates will be provided to the City and IowaDOT in July
so programming of the funds for reconstruction can begin. Finally, discussions continued regarding the short-
term improvements necessary to facilitate a connection at Kimberlite Street. The IowaDOT discussed the
“temporary” improvements that would need to be constructed until the reconstruction project occurs.
Comprehensive Water System Evaluation
A pilot study using the Reverse Osmosis filtration process will likely begin mid to late May.
Trail Connection between Roundabout and Parking Lot
The design team further evaluated Options A & C. It was found that Option A provided grade challenges due
to the required storm sewer pipe. Therefore, design continues to move forward with Option C. Preliminary
plans for this option were provided to City staff on 4/27/2023.
Highway 6 Pedestrian Underpass Inspection
MSA coordinated efforts to complete an inspection of the existing (but closed/buried) pedestrian underpass
just north of the Clear Creek Amana Middle School and under Highway 6. This inspection was completed on
4/10/2023 with report provided to city staff on 4/18/2023.
PROJECT UPDATE
Page 1 of 2