contract agreement · K-3
K-3 - Pay Estimate 4 - Well 5 Pump, Controls, Watermain - Boomerang
Page 2 of 2
Text from the PDF text layer; check the PDF for anything that matters. SUMMARY
Total Approved Total Completed
Contract Price $ 779,550.00 $ 692,333.50
Approved Change Order (list each) Change Order No. 1 $ 8,052.88 $ -
Change Order No. 2 $ 9,081.57 $ 9,081.57
Revised Contract Price $ 796,684.45 $ 701,415.07
Stored $ -
Total Earned $ 701,415.07
Retainage (5%) $ 35,070.75
Total Earned Less Retainage $ 666,344.32
Total Previously Approved (list each) Pay Estimate No. 1 $ 210,331.14
Pay Estimate No. 2 $ 131,643.40
Pay Estimate No. 3 $ 270,110.93
Total Previously Approved $ 612,085.47
Percent Complete 88% Amount Due This Request $ 54,258.85
The amount $54,258.85 is recommended for approval for payment in accordance with the terms of the contract.
Prepared By: Recommended By: Approved By:
Boomerang Corp. Veenstra & Kimm, Inc. Tiffin, Iowa
Signature: Keegan Parizek Signature: Signature:
Name: Keegan Parizek Name: Dave Schechinger Name:
Title: Project Manager Title: Engineer Title:
Date: 05/01/2023 Date: May 1, 2023 Date:
V&K Job No. 5093/1 2 of 2