K-5 - Public Works Equipment Replacement - FY 2023-2024
Page 1 of 1
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-5
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: May 12, 2023
AGENDA ITEM: Discussion and Consideration of FY 2023-2024 Public Works Equipment
Replacement and Council Action as Needed
ACTION: Motion
SYNOPSIS: In November of last year Brian Detert shared with the council the public works
equipment replacement schedule along with five items that would be included in next year’s
budget. Those five items were the Kubota, mini-excavator, skid steer, Ford F-250 and a
skyjack lift. The total amount of the replacement of those items (with trade) was estimated at
$238,000. The Kubota has arrived, the truck has been ordered and Brian found another way
to reach the ceiling in the new public works building (safely) so the lift was replaced with a
floor scrubber. With those adjustments, we budgeted $223,518 in next year’s budget. The
two remaining pieces of equipment (mini-excavator and skid steer) unfortunately, have seen a
price increase from the above budgeted amount and we are now going to be $19,297 short in
next year’s budget. Actually, that number was much higher than that but Brian has worked
very hard to lower that amount by working with a number of new and different vendors to get
the City the best option(s) possible.
Moving forward, we would like to continue to close the gap of the shortfall and continue with
the replacement of these two items. One of the vendors Brian has been working with offers a
lease option. Leasing equipment or vehicles is something the City used to do years ago but
has not done lately. It has been brought up recently when discussing other equipment (with
the market vehicle shortage that was experienced last year) but again, this is something the
City hasn’t done or needed to do for several years. However, in this situation, it would close
the gap for these two items. We have further looked into the leasing option to find there are a
handful of cities that are also starting to do this again simply because of the state of the
equipment and vehicle market we continue to be in. Brian will be at the meeting on Tuesday
night to further discuss this and will have additional numbers to share but with council
approval, we’d like to further pursue this option.
BUDGET ITEM:
MAYOR/COUNCIL ACTION: Motion
ATTACHMENTS:
PREPARED BY: Doug Boldt DATE PREPARED: May 12, 2023