Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
June 2, 2023
PROJECT UPDATE
Highway 6 Pedestrian Underpass Inspection
MSA coordinated efforts to complete an inspection of the existing (but closed/buried) pedestrian underpass
just north of the Clear Creek Amana Middle School and under Highway 6. This inspection was completed on
4/10/2023 with report provided to city staff on 4/18/2023.
MSA bridge engineers are currently preparing an estimate of probable cost for constructing wing wall and
grading to open the box culvert permanently.
DEVELOPMENT ASSISTANCE
Lotus Hill OPD & The State OPD
MSA received the Preliminary Plats for both developments on 5/26/2023. Review are on-going.
Park Place Part 8
Construction on this residential development is on-going. MSA is providing weekly project update reports to
city staff.
Little Clippers Day Care
MSA submitted comments to the developer on 5/9/2023.
Kimberlite Street intersection with U.S. Hwy 6
MMS submitted intersection improvement plans for the Kimberlite Street intersection which includes the
realignment of the street to bypass the parking lot for the City Park. Our Team is reviewing the plans per recent
conversations with IowaDOT.
Upcoming Projects
Major Upcoming Description Next Steps/Schedule
Infrastructure Project
Wastewater Treatment Improvements The current wastewater treatment facility (WWTF) has a Final Compliance with NPDES
chloride compliance schedule. There is not any wastewater Permit required October 1, 2025.
treatment equipment/processes designed to remove chloride
so typically source control is the only economical means of MSA presented its findings on
meeting compliance. The existing treatment facility is at about November 1st. MSA has
50% capacity. However, if the past growth rate continues an prepared a proposed schedule
expansion will be required in the next 6-8 years. for wastewater treatment, water
treatment and water supply
improvement projects.
Deer View Avenue and Tall Grass DOT has requested concurrence from the City on permanent TBD
Avenue & Hwy 6 Intersection improvements to intersection within 5 years of installation of
Improvements temporary traffic signals in 2020. Scope includes both
pedestrian and vehicle accommodations.
PROJECT UPDATE
Page 2 of 2