ON-GOING PROJECTS
North Park Road Improvements
The Concept Statement was submitted to the IowaDOT on 3/21/2023. The Phase I Archaeological survey was
completed and submitted to MSA on 5/2/2023. Wetland delineation has been completed.
MSA attended a joint meeting with the City council and school board to discuss the proposed roundabout and
conceptual site improvements on the school property. In general, the school board is in support of the
roundabout. MSA is completing cost estimates for the “frontage road” on the school property.
Highway 6 Concept and Cost Estimate
The Professional Services Agreement for this work was approved at the last council meeting and executed on
June 21, 2023. Under this contract, MSA will provide preliminary three-dimensional design for roadway and
storm drainage systems to develop a more accurate cost estimate. This cost estimate will be provided to the
IowaDOT in order to program the project as a reconstruction project.
Comprehensive Water System Evaluation
An in-person project update was presented to council at the meeting on 6/6/2023. The 90-day pilot study
began the same day. Anticipated completion of this study and the Preliminary Engineering Report and IDNR
approval by the end of the calendar year.
Trail Connection between Roundabout and Parking Lot
Storm water calculations have been completed for this project in conjunction with the North Park Road storm
water calculations since the trail project lies within the same floodplain as the southern portion of North Park
Road. The plans are nearing 60% complete.
PROJECT UPDATE
Page 1 of 2
Sources
- sharepoint (M-6 - City Engineer Report.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.