Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
August 31, 2023
PROJECT UPDATE
DEVELOPMENT ASSISTANCE – ANDREW INHELDER
Daytona Estates OPD – IN REVIEW
Developer has resubmitted documents for review on 8/31/23. MSA will review and provide a response.
Little Clippers Day Care – AWAITING RESUBMISSION
One outstanding item remaining is a submission of the NPDES.
Lotus Hill OPD & The State OPD – NO FURTHER COMMENTS
MSA provided reviews of the preliminary plats for both developments with no further comments. Comment
regarding sanitary sewer design is remaining. Some comments were made that will be incorporated into the
improvement plans.
Park Place Part 8 - CONSTRUCTED
The punchlist items are complete and the final plat is ready for Council approval pending the Attorney’s legal
documents. Substantial walkthrough completed on 6/26/23. Waiting on final completion notice.
Prairie Village Commercial Part 1, Lot 2 – AWAITING RESUBMITTAL
MSA provided review comments to the developer 7/7/23 with follow up answers to some questions regarding
fire lanes on 7/25/23. Sent Rachel Nardone response to questions about fire lane components through email.
Tiffin Heights West – AWAITING RESUBMITTAL
Tiffin Heights West is currently working on the Developer’s Agreement to accompany the Preliminary Plat. We
have also received the MSA comments for the sanitary and water extensions along Highway 6. We have not
received any comments from the IDOT. We plan to resubmit the plans to both the city and IDOT when we
receive those comments. Comments sent to developer; resubmittal required.
Tiffin West – AWAITING RESUBMITTAL
MSA provided review comments to the developer on 8/2/23 regarding the Phase 1 Plans & Plat along with
comments on the Casey’s Traffic Impact Study. Resubmittal required.
Village Utility Extension – IN REVIEW
Developer has submitted plans, plat, and a prelim sketch of future development on 8/29/23. MSA will review
and provide a response.
PROJECT UPDATE
Page 2 of 3