PROJECT UPDATE
Upcoming Infrastructure Description Next Steps/Schedule
Project
Wastewater Treatment Improvements The current wastewater treatment facility (WWTF) has a Final Compliance with NPDES
chloride compliance schedule. There is not any wastewater Permit required October 1, 2025.
treatment equipment/processes designed to remove chloride
so typically source control is the only economical means of MSA presented its findings on
meeting compliance. The existing treatment facility is at about November 1st 2022. MSA has
50% capacity. However, if the past growth rate continues an prepared a proposed schedule
expansion will be required in the next 6-8 years. for wastewater treatment, water
treatment and water supply
improvement projects.
Deer View Avenue and Tall Grass DOT has requested concurrence from the City on permanent TBD
Avenue & Hwy 6 Intersection improvements to intersection within 5 years of installation of
Improvements temporary traffic signals in 2020. Scope includes both
pedestrian and vehicle accommodations.
Hickory Knoll Sanitary Sewer Reviewing options for sanitary routing to subdivision and TBD
provided opinions of cost to City for review.
Pedestrian light (RRFB) on eastern leg MSA is working on permitting and solicitations for adding an Spring/Summer 2024
of roundabout at Hwy 6 & Park Road. RRFB flashing pedestrian sign on the eastern leg of the
roundabout at Hwy 6 & Park Road. We will be submitting this
over the winter and will seek installation after the trail
improvement project to the soccer fields is complete.
PROJECT UPDATE
Page 3 of 3
Sources
- sharepoint (M-6 - Engineers Report.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.