ON-GOING PROJECTS
North Park Road Improvements – James Watters
MSA submitted an application to the Iowa Clean Air Attainment Program (ICAAP) on September 30, 2023. Time
period for IaDOT to notify City of funding (if selected) is January – March 2024.
MSA is in the process of completing an application for funding through the Iowa Transportation Alternatives
Set-Aside Program (TA Set-aside or TAP). Funding application would be for the funding of the pedestrian
accommodation (multi-use trail, pedestrian underpass, etc) aspects of the project through the Safe Routes to
School Program. Application due date is November 27, 2023.
MSA is coordinating project plans and exhibits with the Army Corp of Engineer’s for wetland and stream
impacts for the project.
Highway 6 Concept and Cost Estimate – Ben Wilkinson
MSA has completed our conceptual design of the project and finalized the draft cost estimate and cost sharing
estimate. After City review, MSA forwarded the cost estimate and concept plans to the DOT for review. Jesse
Tibodeau (Iowa DOT) responded on October 19 and indicated that they were still reviewing but would be in
touch soon to further coordinate the project.
Comprehensive Water System Evaluation – Clint Wienen
MSA will present cost estimates for building type options at the Council Meeting on November 21st. Harn has
received the autopsy result for the pilot test. They will be starting on the pilot report but have not provided a
definitive date on when they will be completed with their report.
Trail Connection between Roundabout and Parking Lot – Andrew Inhelder
Project is ready for bidding. Once council approves and sets dates, project will be bid for construction in Spring
of 2024.
PROJECT UPDATE
Page 1 of 3
Sources
- sharepoint (M-6 - Engineers Report.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.