Text read by the vision model; check the PDF for anything that matters.Non-Rebates For TIFFIN URBAN RENEWAL
TIF Expenditure Amount: 75,497
Tied To Debt: 2017A GO Bond
Tied To Project: Roberts Ferry Road
TIF Expenditure Amount: 83,885
Tied To Debt: 2017A GO Bond
Tied To Project: Park Road/Highway 6 Roundabout
TIF Expenditure Amount: 36,350
Tied To Debt: 2017A GO Bond
Tied To Project: Park Road
TIF Expenditure Amount: 83,885
Tied To Debt: 2017A GO Bond
Tied To Project: Original Town Reconstruction
TIF Expenditure Amount: 58,817
Tied To Debt: 2019A GO Bond
Tied To Project: Park Road/Highway 6 Roundabout
TIF Expenditure Amount: 58,816
Tied To Debt: 2019A GO Bond
Tied To Project: Original Town Reconstruction
TIF Expenditure Amount: 58,816
Tied To Debt: 2019A GO Bond
Tied To Project: Roberts Ferry Road
TIF Expenditure Amount: 58,816
Tied To Debt: 2019A GO Bond
Tied To Project: Forevergreen Road
TIF Expenditure Amount: 517,500
Tied To Debt: 2020A GO Refunding Bond
Tied To Project: Ireland Ave Extension
TIF Expenditure Amount: 19,430
Tied To Debt: 2021A GO Refunding Bond
Tied To Project: Trail Phase 5
TIF Expenditure Amount: 194,300
Tied To Debt: 2021A GO Refunding Bond
Tied To Project: Ireland Ave Extension
TIF Expenditure Amount: 132,124
Tied To Debt: 2021A GO Refunding Bond
Tied To Project: Original Town Reconstruction
TIF Expenditure Amount: 42,746
Tied To Debt: 2021A GO Refunding Bond
Tied To Project: Roberts Ferry Road