other
WS - C - Water Plant Project - Cost Estimate, Layout, Concept
Page 3 of 7
Text read by the vision model; check the PDF for anything that matters.TIFFIN WTP UPGRADES
W/ PRE-ENGINEERED STEEL BUILDING
TIFFIN, IA
ESTIMATE YEAR: 2024
CONSTRUCTION YEAR: 2025
<table>
<tr>
<th>ITEM NO.</th>
<th>ITEM DESCRIPTION</th>
<th>EST. QTY</th>
<th>UNITS</th>
<th>UNIT PRICE</th>
<th>TOTAL PRICE</th>
</tr>
<tr>
<td>32 31 13</td>
<td>Chain Link Fence and Gates</td>
<td>900</td>
<td>LF</td>
<td>$ 45.00</td>
<td>$ 40,500.00</td>
</tr>
<tr>
<td>32 92 19</td>
<td>Seeding</td>
<td>1</td>
<td>ACRES</td>
<td>$ 12,000.00</td>
<td>$ 12,000.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 33</b></td>
</tr>
<tr>
<td>33 10 00</td>
<td>Water Utilities</td>
<td>825</td>
<td>LF</td>
<td>$ 60.00</td>
<td>$ 49,500.00</td>
</tr>
<tr>
<td>33 39 13</td>
<td>Sanitary Sewer Manholes</td>
<td>2</td>
<td>EA</td>
<td>$ 6,000.00</td>
<td>$ 12,000.00</td>
</tr>
<tr>
<td>33 41 13</td>
<td>Sanitary Sewer</td>
<td>100</td>
<td>LF</td>
<td>$ 53.00</td>
<td>$ 5,300.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 40</b></td>
</tr>
<tr>
<td>40 23 34</td>
<td>Water Process Piping System</td>
<td>250</td>
<td>LF</td>
<td>$ 425.00</td>
<td>$ 106,250.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 44</b></td>
</tr>
<tr>
<td>44 42 39.10</td>
<td>RO Equipment</td>
<td>1</td>
<td>LS</td>
<td>$ 1,600,000.00</td>
<td>$ 1,600,000.00</td>
</tr>
<tr>
<td>44 42 40.50</td>
<td>Forced Draft Aerater</td>
<td>1</td>
<td>LS</td>
<td>$ 175,000.00</td>
<td>$ 175,000.00</td>
</tr>
<tr>
<td>44 42 56.50</td>
<td>Centrifugal Booster Pumps</td>
<td>4</td>
<td>EA</td>
<td>$ 20,000.00</td>
<td>$ 80,000.00</td>
</tr>
<tr>
<td>44 42 56.10</td>
<td>Vertical Turbine Pumps</td>
<td>2</td>
<td>EA</td>
<td>$ 23,000.00</td>
<td>$ 46,000.00</td>
</tr>
<tr>
<td>44 42 56.14</td>
<td>Vertical Turbine Rebuild</td>
<td>1</td>
<td>EA</td>
<td>$ 8,500.00</td>
<td>$ 8,500.00</td>
</tr>
<tr>
<td>44 42 76.10</td>
<td>Process Valves</td>
<td>1</td>
<td>LS</td>
<td>$ 60,000.00</td>
<td>$ 60,000.00</td>
</tr>
<tr>
<td>44 44 13.10</td>
<td>Chemical Feed</td>
<td>1</td>
<td>LS</td>
<td>$ 80,000.00</td>
<td>$ 80,000.00</td>
</tr>
<tr>
<td colspan="6"><b>Allowances</b></td>
</tr>
<tr>
<td>A1</td>
<td>Electric Utility</td>
<td>1</td>
<td>LS</td>
<td>$ 15,000.00</td>
<td>$ 15,000.00</td>
</tr>
<tr>
<td>A2</td>
<td>Internet Utility</td>
<td>1</td>
<td>LS</td>
<td>$ 2,500.00</td>
<td>$ 2,500.00</td>
</tr>
<tr>
<td>A3</td>
<td>Phone Utility</td>
<td>1</td>
<td>LS</td>
<td>$ 2,500.00</td>
<td>$ 2,500.00</td>
</tr>
<tr>
<td colspan="5"><b>TOTAL CONSTRUCTION COSTS:</b></td>
<td><b>$ 8,772,630</b></td>
</tr>
<tr>
<td colspan="5">Inflation 3% per year</td>
<td>$ 263,179</td>
</tr>
<tr>
<td colspan="5"><b>CONSTRUCTION SUBTOTAL (2024)</b></td>
<td><b>$ 9,035,809</b></td>
</tr>
<tr>
<td colspan="5">CONTINGENCY 10%</td>
<td>$ 877,263</td>
</tr>
<tr>
<td colspan="5"><b>TOTAL CAPITAL COST</b></td>
<td><b>$ 9,913,071</b></td>
</tr>
</table>
Sources
- sharepoint (WS - C - Water Plant Project - Cost Estimate, Layout, Concept.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.