other
WS - C - Water Plant Project - Cost Estimate, Layout, Concept
Page 2 of 7
Text read by the vision model; check the PDF for anything that matters.TIFFIN WTP UPGRADES
W/ PRE-ENGINEERED STEEL BUILDING
TIFFIN, IA
ESTIMATE YEAR: 2024
CONSTRUCTION YEAR: 2025
<table>
<tr>
<th>ITEM NO.</th>
<th>ITEM DESCRIPTION</th>
<th>EST. QTY</th>
<th>UNITS</th>
<th>UNIT PRICE</th>
<th>TOTAL PRICE</th>
</tr>
<tr>
<td colspan="6"><b>Division 01</b></td>
</tr>
<tr>
<td>DIV 01</td>
<td>Mobilization</td>
<td>1</td>
<td>LS</td>
<td>$ 140,000.00</td>
<td>$ 140,000.00</td>
</tr>
<tr>
<td>DIV 01</td>
<td>Bonds & Insurance</td>
<td>1</td>
<td>LS</td>
<td>$ 105,000.00</td>
<td>$ 105,000.00</td>
</tr>
<tr>
<td>DIV 01</td>
<td>General Conditions</td>
<td>1</td>
<td>LS</td>
<td>$ 384,000.00</td>
<td>$ 384,000.00</td>
</tr>
<tr>
<td>DIV 01</td>
<td>Overhead and Profit</td>
<td>1</td>
<td>LS</td>
<td>$ 1,045,000.00</td>
<td>$ 1,045,000.00</td>
</tr>
<tr>
<td>DIV 01</td>
<td>Project Management</td>
<td>1</td>
<td>LS</td>
<td>$ 105,000.00</td>
<td>$ 105,000.00</td>
</tr>
<tr>
<td>01 33 23</td>
<td>Shop Drawings</td>
<td>1</td>
<td>LS</td>
<td>$ 28,000.00</td>
<td>$ 28,000.00</td>
</tr>
<tr>
<td>01 45 00</td>
<td>Quality Control (Soil and Concrete Testing)</td>
<td>1</td>
<td>LS</td>
<td>$ 20,000.00</td>
<td>$ 20,000.00</td>
</tr>
<tr>
<td>01 52 13</td>
<td>Field Office</td>
<td>16</td>
<td>Months</td>
<td>$ 1,500.00</td>
<td>$ 24,000.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 02</b></td>
</tr>
<tr>
<td>02 41 16</td>
<td>Site Demolition</td>
<td>1</td>
<td>LS</td>
<td>$ 15,000.00</td>
<td>$ 15,000.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 03</b></td>
</tr>
<tr>
<td>03 30 00</td>
<td>CIP Concrete - Driveways</td>
<td>400</td>
<td>SY</td>
<td>$ 45.00</td>
<td>$ 18,000.00</td>
</tr>
<tr>
<td>03 30 00</td>
<td>CIP Concrete - Sidewalks</td>
<td>500</td>
<td>SF</td>
<td>$ 7.50</td>
<td>$ 3,750.00</td>
</tr>
<tr>
<td>03 30 00</td>
<td>CIP Concrete - Water Treatment Plant</td>
<td>260</td>
<td>CY</td>
<td>$ 1,000.00</td>
<td>$ 260,000.00</td>
</tr>
<tr>
<td>4 30 00</td>
<td>CIP Concrete - Clearwell</td>
<td>880</td>
<td>CY</td>
<td>$ 1,200.00</td>
<td>$ 1,056,000.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 05</b></td>
</tr>
<tr>
<td>05 50 00</td>
<td>Metal Fabrications</td>
<td>1</td>
<td>LS</td>
<td>$ 15,000.00</td>
<td>$ 15,000.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 07</b></td>
</tr>
<tr>
<td>07 21 13</td>
<td>Board Insulation</td>
<td>1,600</td>
<td>SF</td>
<td>$ 4.00</td>
<td>$ 6,400.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 08</b></td>
</tr>
<tr>
<td>08 13 13</td>
<td>Doors, Frames, and Hardware</td>
<td>8</td>
<td>EA</td>
<td>$ 5,500.00</td>
<td>$ 44,000.00</td>
</tr>
<tr>
<td>08 36 00</td>
<td>Sectional OHD</td>
<td>4</td>
<td>EA</td>
<td>$ 7,500.00</td>
<td>$ 30,000.00</td>
</tr>
<tr>
<td>08 51 00</td>
<td>Aluminum Windows</td>
<td>8</td>
<td>EA</td>
<td>$ 3,200.00</td>
<td>$ 25,600.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 09</b></td>
</tr>
<tr>
<td>09 96 00</td>
<td>High Performance Coatings</td>
<td>1</td>
<td>LS</td>
<td>$ 75,000.00</td>
<td>$ 75,000.00</td>
</tr>
<tr>
<td>10 44 16</td>
<td>Fire Extinguishers</td>
<td>1</td>
<td>LS</td>
<td>$ 1,000.00</td>
<td>$ 1,000.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 13</b></td>
</tr>
<tr>
<td>13 34 00</td>
<td>Pre-Engineered Steel Structures</td>
<td>5,760</td>
<td>SF</td>
<td>$ 90.00</td>
<td>$ 518,400.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 22</b></td>
</tr>
<tr>
<td>22 00 00</td>
<td>Plumbing</td>
<td>1</td>
<td>LS</td>
<td>$ 75,000.00</td>
<td>$ 75,000.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 23</b></td>
</tr>
<tr>
<td>23 00 00</td>
<td>HVAC</td>
<td>1</td>
<td>LS</td>
<td>$ 150,000.00</td>
<td>$ 150,000.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 26</b></td>
</tr>
<tr>
<td>26 00 00</td>
<td>Electrical Install</td>
<td>1</td>
<td>LS</td>
<td>$ 1,000,000.00</td>
<td>$ 1,000,000.00</td>
</tr>
<tr>
<td>26 05 14</td>
<td>Generator and ATS</td>
<td>1</td>
<td>LS</td>
<td>$ 125,000.00</td>
<td>$ 125,000.00</td>
</tr>
<tr>
<td>26 90 00</td>
<td>Electrical Controls</td>
<td>1</td>
<td>LS</td>
<td>$ 750,000.00</td>
<td>$ 750,000.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 31</b></td>
</tr>
<tr>
<td>31 05 19.13</td>
<td>Geosynthetics for Earthwork</td>
<td>1</td>
<td>LS</td>
<td>$ 4,000.00</td>
<td>$ 4,000.00</td>
</tr>
<tr>
<td>31 11 00</td>
<td>Clearing and Grubbing</td>
<td>1</td>
<td>LS</td>
<td>$ 5,000.00</td>
<td>$ 5,000.00</td>
</tr>
<tr>
<td>31 22 00</td>
<td>Grading/Imported Fill</td>
<td>10,150</td>
<td>CY</td>
<td>$ 32.00</td>
<td>$ 324,800.00</td>
</tr>
<tr>
<td>31 23 16.16</td>
<td>Structural Excavation for Structures</td>
<td>1</td>
<td>LS</td>
<td>$ 50,000.00</td>
<td>$ 50,000.00</td>
</tr>
<tr>
<td>31 23 19</td>
<td>Dewatering</td>
<td>1</td>
<td>LS</td>
<td>$ 30,000.00</td>
<td>$ 30,000.00</td>
</tr>
<tr>
<td>31 25 00</td>
<td>Erosion Control</td>
<td>1</td>
<td>LS</td>
<td>$ 15,000.00</td>
<td>$ 15,000.00</td>
</tr>
<tr>
<td colspan="6"><b>Division 32</b></td>
</tr>
<tr>
<td>32 11 23</td>
<td>Aggregate Base Course</td>
<td>1,481</td>
<td>CY</td>
<td>$ 20.00</td>
<td>$ 29,629.63</td>
</tr>